Question Description
An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared
according to
the Mechanical Engineering exam syllabus. Information about An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer?.
Solutions for An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering.
Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.