An activity has an early start date of the 10th and a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?
  • a)
    Total float for the activity is nine days.
  • b)
    The early finish date of the activity is the end of the day on the 14th.
  • c)
    The late finish date is 25th.
  • d)
    The activity can be completed in two days if the resources devoted to it are double
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
An activity has an early start date of the 10thand a late start date o...
Answer:

Total float for the activity is nine days.

Explanation:

Total float is the amount of time that an activity can be delayed without delaying the project completion date. It is calculated by subtracting the duration of the activity from the difference between the late start date and the early start date.

Given,

Early start date = 10th
Late start date = 19th
Duration of the activity = 4 days

Early finish date = Early start date + Duration of the activity - 1
= 10 + 4 - 1
= 13th

Late finish date = Late start date + Duration of the activity - 1
= 19 + 4 - 1
= 22nd

Therefore,

Total float = Late finish date - Early finish date - Duration of the activity + 1
= 22 - 13 - 4 + 1
= 6 days

So, the correct answer is option A, i.e., Total float for the activity is nine days.
Free Test
Community Answer
An activity has an early start date of the 10thand a late start date o...

Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer?
Question Description
An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer?.
Solutions for An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice An activity has an early start date of the 10thand a late start date of the 19th. The activity has a duration of four days. There are no non-workdays. From the information given, what can be concluded about the activity?a)Total float for the activity is nine days.b)The early finish date of the activity is the end of the day on the 14th.c)The late finish date is 25th.d)The activity can be completed in two days if the resources devoted to it are doubleCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev