Project management is evolved to coordinate and control all project activities in an efficient and cost-effective manner.
The salient features of a project are:
The predecessor to network techniques, the Gantt chart was developed, during world war I, by Henry L Gantt, for the purpose of production scheduling. An example of a Gantt chart is shown below.
The Gantt chart was later modified to a bar chart, which was an important tool in both the project and production schedule.
The bar charts then developed into milestone charts and next into network techniques (such as CPM and PERT). The bar chart didn't give information about critical activity and interdependence among activities. A bar chart is activity-oriented, while a milestone chart is event-oriented.
A network is the graphical representation of the project activities arranged in a logical sequence and depicting all the inter-relationships among them. A network consists of activities and events.
Each node is represented by a circle and numbered by using Fulkerson's Rule. The following steps are involved in the numbering of the nodes:
An illustration of Fulkerson's Rule of numbering the events is shown in. As a recommendation, it must be noted that most of the projects are liable for modifications, and hence there should be scope for adding more events and numbering them without causing any inconsistency in the network. This is achieved by skipping the numbers (i.e. 10, 20, 30).
Rules for drawing a network diagram
Rule 1: Each activity is represented by one and only one arrow in the network.
Rule 2: No two activities can be identified by the same end events.
Rule 3: Precedence relationships among all activities must always be maintained.
Rule 4: Dummy activities can be used to maintain precedence relationships only when actually required. Their use should be minimized in the network diagram.
Rule 5: Looping among the activities must be avoided.
This is based on the deterministic approach in which only a one-time estimate is made for activity completion. The CPM (critical path method) system of networking is used when the activity time estimates are deterministic in nature. For each activity, a single value of time required for its execution is estimated. Time estimates can easily be converted into cost data in this technique. CPM is an activity-oriented technique.
Activity times
Float
Float denotes the range within which activity time or its finish time may fluctuate without
effecting the completion of the project.
An Activity-On-Node (AON) Network
5 videos|19 docs|16 tests
|
1. What is CPM in Civil Engineering? |
2. How does CPM benefit civil engineering projects? |
3. What are the key components of a CPM network analysis in civil engineering? |
4. How is the critical path determined in CPM analysis? |
5. Can CPM be used for large-scale civil engineering projects? |
|
Explore Courses for Civil Engineering (CE) exam
|