Method of interpolation of contours:
The process of locating the contours proportionately between the plotted points is termed interpolation. Interpolation may be done by:
By arithmetical calculation
Let A and B be two corners of the squares. The RL of A is 98.75 m, and that of B 100.75 m. the horizontal distance between A and B is 10m.
Horizontal distance between A and B = 10m
Vertical difference A and B = 100.75-98.75=2m
Let a contour of 99.00 m be required. Then,
Difference of level between A and 99.00m contour = 99.00-98.75=0.25m
Therefore, distance of 99.00 m contour line form A= 10/2 *0.25=1.25m
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a point of RL of 99.00 m.
Similarly, the other points can be located.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts. AB is bisected at C and a perpendicular is drawn at this point. A point O is selected on this perpendicular line and then radial lines are drawn from O to the divisions on AB. After this lines 1-1, 2-2, 3-3….are drawn parallel to AB. These lines serve as guide lines. Boundary line and every fifth the line is marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and 100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will represent 95,100,105, etc. The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’ at 100.25. Line ‘ab’ should be parallel to AB. Now the points 94, 96, 98,100 are picked through to obtain the positions of the required contours.
Method of interpolation of contours:
The process of locating the contours proportionately between the plotted points is termed interpolation. Interpolation may be done by:
By arithmetical calculation
Let A and B be two corners of the squares. The RL of A is 98.75 m, and that of B 100.75 m. the horizontal distance between A and B is 10m.
Horizontal distance between A and B = 10m
Vertical difference A and B = 100.75-98.75=2m
Let a contour of 99.00 m be required. Then,
Difference of level between A and 99.00m contour = 99.00-98.75=0.25m
Therefore, distance of 99.00 m contour line form A= 10/2 *0.25=1.25m
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a point of RL of 99.00 m.
Similarly, the other points can be located.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts. AB is bisected at C and a perpendicular is drawn at this point. A point O is selected on this perpendicular line and then radial lines are drawn from O to the divisions on AB. After this lines 1-1, 2-2, 3-3….are drawn parallel to AB. These lines serve as guide lines. Boundary line and every fifth the line is marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and 100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will represent 95,100,105, etc. The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’ at 100.25. Line ‘ab’ should be parallel to AB. Now the points 94, 96, 98,100 are picked through to obtain the positions of the required contours.
1. What is interpolation of contours in surveying and levelling? |
2. What is the importance of interpolation of contours in agricultural engineering? |
3. What are the different methods of contour interpolation? |
4. How is contour interpolation used in precision agriculture? |
5. What are some common challenges associated with contour interpolation in surveying and levelling? |
|
Explore Courses for Agricultural Engineering exam
|