Try yourself: Consider the given project network, where numbers along various activities represent normal time. The free float on activity 4-6 and the project duration, respectively, are [2014]
Try yourself: For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below. If duration of activity f is changed to 10 days, then the critical path for the project is [2012]
Try yourself: The project activities, precedence relationships and durations are described in the table. The critical path of the project is [2010]
Try yourself: For the network below, the objective is to find the length of the shortest path from node P to node G. Let dij be the length of directed arc from node i to node j.Let sj, be the length of the shortest path from P to node j. Which of the following equations can be used to find SG? [2008]
Try yourself: A project has six activities (A t o F ) w it h respective activity durations 7,5,6,6,8,4 days.The network has three path A-B, C-D and EF. All the activities can be crashed with the same crash cost per day.The number of activities that need to be crashed to reduce the project duration by 1 day is [2005]
Try yourself: An assembly activity is represented on an Operation Process Chart by the symbol [2005]
Try yourself: A project consists of activities A to M shown in the net in the following figure with the duration of the activities marked in daysThe project can be completed [2003]

Try yourself: The symbol used for Transport in work study is [2003]
Try yourself: In the construction of networks , dummy activities are introduced in order to [1990]
Try yourself: In PERT chart, the activity time distribution is [2016]
Try yourself: Consider the following PERT network: The optimistic time, most likely time and pessimistic time of all the activities are given in the table below:The critical path duration of the network (in days) is [2009]


Try yourself: The expected time (te) of a PERT activity in terms of optimistic time (t0), pessimistic time (tp) and most likely time (tl) is given by [2006]
Try yourself: Consider a PERT network for a project involving six tasks (a to f) The expected completion time of the project is [2006]

Try yourself: In PERT analysis a critical activity has [2004]
Try yourself: A dummy activity is used in PERT network to describe
Try yourself: In PERT, the distribution of activity times is assumed to be [1995]
| 1. What are the key concepts of network models in mechanical engineering? | ![]() |
| 2. How are network models applied in project management? | ![]() |
| 3. What is the significance of critical path analysis in network models? | ![]() |
| 4. Can network models be used for optimization in mechanical engineering systems? | ![]() |
| 5. What types of problems can be solved using network models in mechanical engineering? | ![]() |