Table of contents |
|
Overview |
|
Anticipatory Breach of Contract |
|
Actual Breach of Contract |
|
Suit For Damages |
|
Penalty and Liquidated Damages (Section 74) |
|
Ways of Anticipatory Breach:
Examples:
Legal Provision:
Section 39 of the Indian Contract Act addresses anticipatory breach, stating that when a party refuses or is unable to perform their promise, the other party may terminate the contract unless they indicate their acceptance of its continuation.
Effects of Anticipatory Breach:
Actual breach of contract refers to the situation where one party fails to perform their contractual obligations by the agreed-upon date. In a lawful contract, both parties are obligated to fulfill their respective promises. However, when one party refuses to do so, they commit a breach of contract, giving the other party the right to take legal action against them.
Remedies for Breach of Contract
Available Remedies:
Section 73 of the Act outlines how to determine the amount of compensation for a breach of contract. When a contract is breached, the injured party is entitled to receive compensation from the party at fault for any loss or damage caused by the breach.
Compensation can be claimed for:
The aggrieved party is obligated to take reasonable steps to minimize the loss. Remote or indirect losses are not compensable.
Types of Damages:
(i) Ordinary Damages:
When a contract is breached, the injured party is entitled to compensation for any loss or damage that naturally arises from the breach or that the parties anticipated would result from the breach at the time of making the contract. This compensation is not intended for remote or indirect losses or damages caused by the breach, as outlined in Section 73 of the Indian Contract Act and the precedent set in Hadley vs. Baxendale.
Hadley vs. Baxendale :
(ii) Special Damages in Contract Law :
(iii) Vindictive or Exemplary Damages
These damages are applicable only in two specific situations:
(a) Breach of Promise to Marry: When there is a breach of promise to marry, it is considered an injury to the feelings of the aggrieved party. In such cases, vindictive or exemplary damages may be awarded to compensate for the emotional distress caused.
(b) Wrongful Dishonour of Cheque by Banker: Exemplary damages may be awarded in cases of wrongful dishonour of a customer's cheque by a banker. This is because such wrongful dishonour can cause significant injury, leading to a loss of credit and reputation for the cheque drawer. Even if a businessman does not suffer pecuniary loss, they may still be entitled to exemplary damages. However, a non-trader can only claim heavy damages in similar circumstances if they can prove special damages. This principle was established in the case of Gibbons v Westminster Bank.
(iv) Nominal Damages: Nominal damages are granted when the plaintiff demonstrates that there has been a breach of contract, but no substantial harm has been suffered. These damages are awarded to affirm the right to seek a decree for the breach, and the amount may be more symbolic than a precise monetary figure.
(v) Damages for Deterioration Caused by Delay: In instances where goods have deteriorated due to delay, carriers can be held liable for damages even without prior notice. Deterioration encompasses not only physical damage to the goods but also the loss of a special sales opportunity.
(vi) Pre-fixed Damages: Parties to a contract may agree in advance on a specific amount to be paid as damages in the event of a breach. These amounts can be categorized as:
Section 74 of the Indian Contract Act stipulates that if a sum is specified in a contract as the amount to be paid in case of a breach, the aggrieved party is entitled to receive reasonable compensation not exceeding the specified amount.
Example 6: If a contract specifies a penalty of ₹ 1,00,000 for a breach, but the actual loss suffered is ₹ 70,000, only ₹ 70,000 can be claimed as damages. Conversely, if the loss is ₹ 1,50,000, only ₹ 1,00,000 can be recovered.
Example 7: If X promises to pay ₹ 10,000 to Y, a priest, as charity, and Y incurs expenses of ₹ 7,500 for repairing a temple based on X's promise, Y can claim ₹ 7,500 from X.
The parties to a contract may specify in advance the amount of compensation that will be payable in the event of a failure to perform the contract. This raises the question of whether the courts will accept this figure as the measure of damages.
English Law: In English law, the fixed sum in a contract can be seen either as liquidated damages or as a penalty.
Indian Law: Indian law does not differentiate between "penalty" and "liquidated damages." Courts in India award only reasonable compensation not exceeding the specified sum in the contract.
Exception: In cases where a person gives a bond to the Central or State government for the performance of a public duty or act in the public interest, breaching any conditions of such an instrument can lead to liability for the entire specified amount.
Liquidated damages and penalties are both types of compensation that are payable when a contract is breached. However, there are key differences between the two.
1. Definition:
2. Key Distinctions:
3. Legal Perspectives:
51 videos|110 docs|57 tests
|
1. What is anticipatory breach of contract and how does it differ from actual breach? | ![]() |
2. What remedies are available for a breach of contract? | ![]() |
3. What are penalty and liquidated damages under Section 74 of the Indian Contract Act? | ![]() |
4. How can a party prove actual damages in a breach of contract suit? | ![]() |
5. What is the difference between compensatory damages and punitive damages? | ![]() |