CLAT Exam  >  CLAT Notes  >  Quantitative Techniques for CLAT  >  Time and Work

Time and Work | Quantitative Techniques for CLAT PDF Download

Introduction 

Work is defined as something which has an effect or outcome; often the one desired or expected. The basic concept of Time and Work is similar to that across all Arithmetic topics, i.e. the concept of Proportionality.

Efficiency is inversely proportional to the Time taken when the amount of work done is constant.

What is Time and Work?

Time and Work | Quantitative Techniques for CLAT

The important terms related to time and work are given below:

  • Time Taken: Rate of work and time are inversely proportional to each other. Thus, R = 1/T
  • Work Done: It takes (T) time to complete a certain amount of work (W). The number of units of work done per unit time. Thus, Work Done (W) = Time (T) * Rate of Work (R)
  • Negative Work: Assume that there are two people A and B who have been assigned to build a table. Here, work refers to the building of a table. Also, assume that there is another person C who is assigned the task of damaging the table. Now, work done by C is termed as negative work as C is effectively lowering the amount of work done by A and B.

Types of Questions from Time and Work

There are some specific types of questions from Time and Work that usually come in exams. Some of the important types of questions from time and work are as follows:

Time and Work | Quantitative Techniques for CLAT

  • Time and Work Questions involving individual efficiencies
    • In such questions, the rates at which some individuals complete work alone are given and you are required to calculate the rate at which they can complete the work together and vice versa.
  • Time and Work Questions involving group efficiencies 
    • Till now, we have looked at problem types where individuals were working, in this type of question, we will now look at problems where people with the same efficiencies are working in groups.

To solve problems on ‘time and work’ the following simple facts should be remembered:

  • If a person can do work in 5 days, then in one day he will do 1/5th of the whole work. Conversely, if a man can do 1/5th of the work in one day, he will complete the whole work in 5 days.
  • If the number of men engaged to do a piece of work be increased in a certain ratio, the time required to do the same work will be decreased in the same ratio and vice versa. Thus if the number of men is changed in the ratio of 3:7, the time required will be changed in the ratio of 7:3.

Time and Work | Quantitative Techniques for CLAT

  • If A is twice as good a workman as B then A will take one-half of the time taken by B to do a certain piece of work.
  • To sum up if M1 persons working T1 hours a day can do W1 work in D1 days and M2 persons working H2 hours a day can do W2 work in D2 days, then the following equation will hold good.
    Time and Work | Quantitative Techniques for CLAT

Example . A does work in 10 days and B does the same work in 15 days. How many days they will take to do the work together.

Sol. A does the work in 10 days, so A’s one-day work = 1/10

B does the work in 15 days, so B’s one day work = 1/15

Work done by A and B in one day = 1/10 + 1/15 = 5/30 = 1/6

Thus, A and B together will be able to finish the work in 6 days.

Question for Time and Work
Try yourself: A can finish a work in 18 days and B can finish the same work in 9 days. If they work together, what part of the work will they be able to finish in a day. 
View Solution

Concept of Efficiency

Time and Work | Quantitative Techniques for CLAT

Efficiency denotes the amount of work done by any person in 1 day. We use this concept to compare the quality of a worker, i.e., if a worker is more efficient than any other worker, then we can say he/she can do more work in 1 day as compared to other workers.

  • The ratio of the efficiencies of two workers is proportional to the time taken by them to complete a work.
  • If a worker is less efficient than he/she will take more time to complete the work.
  • If a worker is more efficient than he/she will take less time to complete the work.
  • The number of

Example: - A is 3 times as efficient as B. If B alone can complete the work in 12 days, then A alone can complete the work in how many days?

Solution: - According to the question, the ratio of the efficiency of A and B is 3 : 1

We know that the ratio of the efficiency is inversely proportional to the ratio of the time taken

So, the ratio of the time taken by A and B to complete the work will be 1 : 3

Let us assume A alone completes the work in x days and B alone completes the work in 3x days

3x=12

x=4

Therefore, A alone can complete the work in 4 days.

Note: The concept of efficiency is widely used to equate the works of men, women, and children.

Tips and Tricks to Solve 

Tip 1: Work and Wages Concept: Ratio of wages of persons doing work is directly proportional to the ratio of efficiency of the persons.

Tip 2: If A can do a piece of work in 10 days, then in 1 day, A will do 1/10 part of total work.

Tip 3: If A is thrice as good as B, then

  1. In a given amount of time, A will be able to do 3 times the work B does. Ratio of work done by A and B (at the same time) = 3 : 1.
  2. For the same amount of work, B will take thrice the time as much as A takes. Ratio of time taken by A and B (same work done) = 1 : 3.

Tip  4: Efficiency is directly proportional to the work done and Inversely Proportional to the time taken.

Tip  5: The number of days or time required to complete the work by A and B both is equal to the ab/a+b.

Solved Examples

Example 1. A tyre has two punctures. The first puncture alone can empty the tyre in 9 minutes and 2nd puncture alone can empty the tyre in 6 minutes. How long will both the punctures take to flat the tyre. 

Sol. The first puncture takes 9 minutes to flatten the tyre, so first puncture’s one-minute work = 1/ 9  The second puncture takes 6 minutes to flatten that tyre, so second puncture’s one-minute work = 1/6

So work done by both punctures in one minute = 1/9 + 1/6 = 5/18

Thus, both punctures together will take 18/5 minutes to flatten the tyre.

Example 2. A and B together can finish a job in 15 days. If A alone can finish the job in 25 days, in how many days can B alone finish the job. 

Sol. A and B together can finish the job in 15 days, so their one day work = 1/15
A alone can finish the job in 25 days, so A’s one day work = 1/25


B’s one day work =  Time and Work | Quantitative Techniques for CLAT

Thus, B alone can finish the job in 75/2 days.

Example 3.  A and B together can build a house in 25 days. They work together for 15 days and then B goes away. A finishes the rest of the work in 20 days. How long will each take to finish the job working separately?

Sol. A+B can finish the work in 25 days, so one day work = 1/25
They work together for 15 days, so the work done by A+B in 15 days = Time and Work | Quantitative Techniques for CLAT


Remaining job = Time and Work | Quantitative Techniques for CLAT  

To complete 2/5 of work in 20 days, A can complete one work in Time and Work | Quantitative Techniques for CLAT = 50 days 

B’s one day work = 1/25 – 1/50 = 1/50    

So B can finish the whole work in 50 days.

Question for Time and Work
Try yourself:
A man can do a job in 5 days but with the help of his son he can do it is 3 days. In what time can the son do it alone. 
View Solution

Example 4.   A can finish a job in 10 days, B in 12 days and C in 10 days. In how many days will they finish the job if they work together. 

Sol. A’s one day work = 1/10

B’s one day work = 1/12

C’s one day work = 1/10

A+B+C’s one day work = 1/10 + 1/12 + 1/10 = (6+5+6)/60 = 17/60

Thus, together they can complete the work in 60/17 days.

Questions on Pipes and Cisterns

Example 5. Tap A can fill a tank in 8 hours. Outlet B can empty the tank in 12 hours. If both are kept open, how long will it take to fill the tank? 

Sol. Tap A can fill the tank in 8 hours, so Tap A’s one-hour work = 1/8


Tap B can empty the tank in 12 hours, so Tap B’s one hour work = 1/12

Tap A and Tap B’s one hour work = 1/8 – 1/12 = (3 – 2) / 24  = 1/24

Thus, the tank will be full after 24 hours.

Example 6. 8 Taps can fill a reservoir in 90 minutes. In how much time 12 taps can fill up the same reservoir if all the taps have equal capacity. 

Sol. 8 taps fill the reservoir in 90 minutes

One taps fill the reservoir in 90 x 8 minutes.

12 taps fill the reservoir in = (90 x 8) / 12 = 60 minutes.

Question for Time and Work
Try yourself:Tap A and B can separately fill a tank in 10 hours and 15 hours respectively. If both the taps are opened together, how long will it take for the tank to be full?
View Solution

Example 7. Pipe A can fill a tank in 3 hours. Pipe B can fill it in 4 hours. An outlet pipe C can empty the filled-in tank in 6 hours. If all the three pipes are kept open simultaneously, in how many hours will the tank be half full? 

Sol. Pipe A can fill the tank in 3 hours, so Pipe A will fill in one hour =  1/3

Pipe B can fill the tank in 4 hours, so pipe B will fill in one hour = 1/4

Pipe C can empty the tank in 6 hours, so in one-hour pipe C will empty = 1/6

Pipe A + Pipe B + Pipe C = 1/3 + 1/4 - 1/6 = Time and Work | Quantitative Techniques for CLAT

So three pipes can fill the tank in 12/5 hours.

Thus, ½ tank will be filled in ½ x 12/5 = 6/5 hours.

Question for Time and Work
Try yourself:Ex.13. Tap A fills a tank in 2 hours. Outlets B and C can empty the tank in 4 hours and 3 hours respectively. If the tank is empty and A and B are opened, how long will it take to fill the tank. After the tank is full A, B, C are all opened, in how many hours will the tank be empty. 
View Solution

The document Time and Work | Quantitative Techniques for CLAT is a part of the CLAT Course Quantitative Techniques for CLAT.
All you need of CLAT at this link: CLAT
56 videos|104 docs|95 tests

Top Courses for CLAT

FAQs on Time and Work - Quantitative Techniques for CLAT

1. What is time and work?
Ans. Time and work is a concept in mathematics that deals with the relationship between the time taken to complete a task and the work done. It involves calculating the amount of work done by a person or a group of people in a given time period.
2. How do you calculate the time taken to complete a task?
Ans. To calculate the time taken to complete a task, you need to know the amount of work to be done and the rate at which the work is being done. You can then use the formula: Time = Work / Rate.
3. What is the formula for calculating work?
Ans. The formula for calculating work is: Work = Time x Rate. This formula allows you to find the amount of work done by multiplying the time taken to complete the task with the rate at which the work is being done.
4. Can time and work problems involve multiple people working together?
Ans. Yes, time and work problems can involve multiple people working together. In such cases, the concept of work done by each person in a given time period is used to calculate the total work done by the group. The formula for calculating work remains the same, but the rate is adjusted based on the number of people working.
5. How can time and work problems be solved using ratios?
Ans. Time and work problems can be solved using ratios by considering the ratio of work done to the time taken by each person. By setting up and solving equations based on these ratios, you can find the individual rates of work and then calculate the total work done.
56 videos|104 docs|95 tests
Download as PDF
Explore Courses for CLAT exam

Top Courses for CLAT

Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev
Related Searches

Free

,

Important questions

,

pdf

,

Objective type Questions

,

Previous Year Questions with Solutions

,

mock tests for examination

,

Semester Notes

,

Time and Work | Quantitative Techniques for CLAT

,

Exam

,

ppt

,

Extra Questions

,

Sample Paper

,

Summary

,

practice quizzes

,

Time and Work | Quantitative Techniques for CLAT

,

Time and Work | Quantitative Techniques for CLAT

,

video lectures

,

study material

,

shortcuts and tricks

,

Viva Questions

,

MCQs

,

past year papers

;