An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:
For line balancing the number of work stations required for the activities M, E and T would respectively be 
  • a)
    2, 3, 1 
  • b)
    3, 2, 1
  • c)
    2, 4, 2
  • d)
    2, 1, 3
Correct answer is option 'A'. Can you explain this answer?
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer?
Question Description
An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer?.
Solutions for An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer?, a detailed solution for An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce 80 units during a regular 8-hour shift. This operation consists of three activities as below:For line balancing the number of work stations required for the activities M, E and T would respectively bea)2, 3, 1b)3, 2, 1c)2, 4, 2d)2, 1, 3Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev