A manufacturer's master product schedule of a product is given below:
Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order for 
  • a)
    400 components in week-l    
  • b)
    400 components in week-3  
  • c)
    200 components in week-l and 200 components in week-3  
  • d)
    400 components in week-5 
Correct answer is option 'B'. Can you explain this answer?
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer?
Question Description
A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer?.
Solutions for A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A manufacturer's master product schedule of a product is given below:Each product requires a purchased component A in its subassembly. Before the start of week-1, there are 400 components of type A in stock. The lead time to procure this component is 2 weeks and the order quantity is 400. Number of components A per product is only one. The manufacturer should place the order fora)400 components in week-l b)400 components in week-3 c)200 components in week-l and 200 components in week-3 d)400 components in week-5Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev