Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  The Product structure of an assembly P is sho... Start Learning for Free
The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:​Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is
[2008]
  • a)
    1000
  • b)
    1200
  • c)
    2200
  • d)
    2400
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
The Product structure of an assembly P is shown in the figure.Estimate...
The M .R.P. f or R is given by
If 6P – 12800 ≥ 0 then the capacity is f easible \ Minimization ,
6P = 12800⇒
  P ≌ 2200
View all questions of this test
Most Upvoted Answer
The Product structure of an assembly P is shown in the figure.Estimate...
The M .R.P. f or R is given by
If 6P – 12800 ≥ 0 then the capacity is f easible \ Minimization ,
6P = 12800⇒
  P ≌ 2200
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer?
Question Description
The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer?.
Solutions for The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer?, a detailed solution for The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The Product structure of an assembly P is shown in the figure.Estimated demand for end product P is as follows:Ignore lead times for assembly and subassembly. Production capacity (per week) for component R is the bottleneck operation.Starting with zero inventory, the smallest capacity that will ensure a feasible production plan up to week 6 is[2008]a)1000b)1200c)2200d)2400Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev