Which one of the following statements is not correct? 
  • a)
    PERT is activity oriented and CPM is event oriented  
  • b)
    In PERT, three time estimates are made, whereas in CPM only one time estimate is made  
  • c)
    In PERT slack is calculated whereas in CPM floats are calculated  
  • d)
    Both PERT and CPM are used for project situations 
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Which one of the following statements is not correct?a)PERT is activit...
(a) PERT → Event oriented
CPM → Activity oriented
(b) PERT → 3 tim e esti mates are made 

CPM → on ly one ti me estimate
(c) In PERT slack is calculated, CPM floats calculated
(d) Both PERT and CPM are used for project situation. 
View all questions of this test
Most Upvoted Answer
Which one of the following statements is not correct?a)PERT is activit...
Introduction:
PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) are project management tools used to plan, schedule, and control projects. While both PERT and CPM have similarities, there are certain differences between them.

Explanation:
The correct answer is option 'A': PERT is activity-oriented and CPM is event-oriented. This statement is not correct because PERT is event-oriented, not activity-oriented. Here is a detailed explanation of each statement:

a) PERT is activity-oriented and CPM is event-oriented:
- PERT (Program Evaluation and Review Technique) is event-oriented, where the focus is on determining the sequence of events or milestones in a project.
- CPM (Critical Path Method) is also event-oriented, where the focus is on identifying the critical path, which is the longest sequence of activities that determines the project duration.

b) In PERT, three time estimates are made, whereas in CPM only one time estimate is made:
- In PERT, three time estimates are made for each activity: optimistic time (O), pessimistic time (P), and most likely time (M). These estimates are used to calculate the expected time (TE) using the formula: TE = (O + 4M + P) / 6.
- In CPM, only one time estimate is made for each activity, which is the most likely time (M). This estimate is used to calculate the project duration.

c) In PERT slack is calculated whereas in CPM floats are calculated:
- In PERT, slack is calculated to determine the flexibility or float time for non-critical activities. Slack is the amount of time an activity can be delayed without affecting the project duration.
- In CPM, floats are calculated to determine the flexibility or float time for both non-critical and critical activities. Floats include total float, which is the amount of time an activity can be delayed without delaying the project, and free float, which is the amount of time an activity can be delayed without delaying the early start of its successor activities.

d) Both PERT and CPM are used for project situations:
- This statement is correct. Both PERT and CPM are widely used project management techniques to plan, schedule, and control projects. They help in identifying critical activities, determining project duration, allocating resources, and managing project risks.

Conclusion:
In conclusion, the statement that is not correct is option 'A': PERT is activity-oriented and CPM is event-oriented. PERT is event-oriented, and both PERT and CPM are used for project situations.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer?
Question Description
Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which one of the following statements is not correct?a)PERT is activity oriented and CPM is event oriented b)In PERT, three time estimates are made, whereas in CPM only one time estimate is made c)In PERT slack is calculated whereas in CPM floats are calculated d)Both PERT and CPM are used for project situationsCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev