For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated as 
C0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.
    Correct answer is '(0.7)'. Can you explain this answer?
    Verified Answer
    For routing of flood in a given channel using the Muskingum method, tw...
    In Muskingum flood routing method 
    C0 + C1 + C2 = 1
    ⇒ 
    View all questions of this test
    Most Upvoted Answer
    For routing of flood in a given channel using the Muskingum method, tw...
    0.3 and C1 = 0.4.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer?
    Question Description
    For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer?.
    Solutions for For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer?, a detailed solution for For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer? has been provided alongside types of For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For routing of flood in a given channel using the Muskingum method, two of the routing coefficients are estimated asC0 =−0.25 and C1 = 0.55. The value of the third coefficient C2 would be _________.Correct answer is '(0.7)'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev