    Risk = The probability of a flood to occur at least once in n-successive years.
    View all questions of this test
    Most Upvoted Answer
    A culvert is designed for a flood frequency of 100 years and a useful ...
    Understanding the Risk Involved in Culvert Design
    Understanding the Components Involved:
    - Flood Frequency: The flood frequency of 100 years means that there is a 1% chance of a flood of this magnitude occurring in any given year.
    - Useful Life: The useful life of the culvert is 20 years, after which it may need to be replaced or repaired.

    Calculating the Risk
    Risk can be calculated as the probability of an event occurring multiplied by the consequences of that event. In this case, the risk involved in the design of the culvert can be calculated as follows:
    Risk = (1 - (1 - 1/100)^20) x 100%
    - (1 - 1/100) represents the probability of not experiencing a flood in any given year.
    - (1 - 1/100)^20 represents the probability of not experiencing a flood in 20 years.
    - 1 - (1 - 1/100)^20 represents the probability of experiencing at least one flood in 20 years.

    Calculating the Risk Percentage
    By plugging the values into the formula, we get:
    Risk = (1 - (1 - 1/100)^20) x 100%
    Risk = (1 - (0.99)^20) x 100%
    Risk = (1 - 0.818) x 100%
    Risk = 0.182 x 100%
    Risk = 18.20%
    Therefore, the risk involved in the design of the culvert is 18.20%, indicating the likelihood of experiencing at least one flood event within the useful life of the culvert.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer?
    Question Description
    A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer?.
    Solutions for A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer?, a detailed solution for A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer? has been provided alongside types of A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A culvert is designed for a flood frequency of 100 years and a useful life of 20 years. The risk involved in the design of the culvert (in percentage, up to two decimal places) is ___________Correct answer is '(18.20)'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev