Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  A dam is designed for a 50-year flood. Assumi... Start Learning for Free
A dam is designed for a 50-year flood. Assuming a construction period of 8 years,
the percentage risk that the dam may fail before the completion of the construction
is (round off to 2 decimal places)
ANS 14.50 to 15.10?
Most Upvoted Answer
A dam is designed for a 50-year flood. Assuming a construction period ...
**Percentage Risk of Dam Failure during Construction**

To calculate the percentage risk that the dam may fail before the completion of the construction, we need to consider the design flood return period and the construction period.

**Design Flood Return Period:**

The dam is designed for a 50-year flood. This means that the dam is designed to withstand a flood event that has a 2% chance of occurring in any given year. The design flood return period indicates the level of flood the dam is expected to withstand without failure.

**Construction Period:**

The construction period is given as 8 years. During this time, the dam is being built and may not have reached its full capacity or strength. The risk of failure is higher during the construction phase compared to when the dam is completed.

**Calculating the Risk:**

To calculate the percentage risk of dam failure during construction, we need to consider the probability of a flood event occurring during the construction period. Since the dam is designed for a 50-year flood, we can assume that the probability of a flood event occurring in any given year is 2%.

The probability of a flood event occurring during the construction period can be calculated using the formula:

P = 1 - (1 - p)^n

Where P is the probability of a flood event occurring during the construction period, p is the probability of a flood event occurring in any given year, and n is the number of years in the construction period.

Substituting the values:

P = 1 - (1 - 0.02)^8

P ≈ 0.1450

Therefore, the percentage risk of dam failure during construction is approximately 14.50%.

**Conclusion:**

The percentage risk that the dam may fail before the completion of the construction is approximately 14.50%. This means that there is a 14.50% chance of a flood event occurring during the 8-year construction period, which could potentially lead to dam failure. It is important to consider this risk during the planning and construction phases to ensure appropriate mitigation measures are in place to minimize the potential consequences of a flood event.
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10?
Question Description
A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10?.
Solutions for A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10? defined & explained in the simplest way possible. Besides giving the explanation of A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10?, a detailed solution for A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10? has been provided alongside types of A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10? theory, EduRev gives you an ample number of questions to practice A dam is designed for a 50-year flood. Assuming a construction period of 8 years,the percentage risk that the dam may fail before the completion of the constructionis (round off to 2 decimal places)ANS 14.50 to 15.10? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev