Question Description
A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A and B start working together on a project and both have the same efficiency in the beginning. However the efficiency of A decreases to 0.6 times the usual after working for 2 hours. If the project can be finished in 120 man hours, then find the minimum number of days required to finish the work if both do an equal manhours of work each day and the sum of the total number of hours of work by both each day is 12. [ Initial efficiency of A = Efficiency of B = 1 man hour].a)10 daysb)12 daysc)16 daysd)Cannot be determinedCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.