Quant Exam  >  Quant Questions  >  12 men complete a work in 18 days. 6 days aft... Start Learning for Free
12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?
  • a)
    10 days
  • b)
    12 days
  • c)
    15 days
  • d)
    9 days
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
12 men complete a work in 18 days. 6 days after they had started worki...
12 × 18 = 12 × 6 + 16 × t Æ t = 9
View all questions of this test
Most Upvoted Answer
12 men complete a work in 18 days. 6 days after they had started worki...
Understanding the Work Rate
12 men can complete the work in 18 days. Therefore, the total work can be calculated as:
- Total Work = 12 men * 18 days = 216 man-days.
Work Completed in 6 Days
In the first 6 days, the 12 men work together to complete:
- Work Done = 12 men * 6 days = 72 man-days.
Remaining Work After 6 Days
The remaining work after 6 days is:
- Remaining Work = Total Work - Work Done = 216 man-days - 72 man-days = 144 man-days.
Work Rate After 4 Men Join
After 6 days, 4 more men join the original 12, making a total of 16 men.
- Work Rate of 16 men = 16 men/day.
Calculating Time to Complete Remaining Work
To find out how many days the 16 men will take to complete the remaining 144 man-days of work:
- Days Needed = Remaining Work / Work Rate = 144 man-days / 16 men = 9 days.
Conclusion
Thus, after the initial 6 days of work, the 16 men will take an additional 9 days to finish the remaining work. Hence, the correct answer is option 'D'.
Explore Courses for Quant exam

Similar Quant Doubts

12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 12 men complete a work in 18 days. 6 days after they had started working, 4 men join them. Howmany more days will all of them take to complete the remaining work?a)10 daysb)12 daysc)15 daysd)9 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev