Quant Exam  >  Quant Questions  >  20 men can complete a piece of work in 14 day... Start Learning for Free
20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?
  • a)
    18 days
  • b)
    20 days
  • c)
    8 days
  • d)
    12 days
  • e)
    10 days
Correct answer is option 'E'. Can you explain this answer?
Verified Answer
20 men can complete a piece of work in 14 days. 7 men started the work...
Let (7+7) complete remaining work in x days.
So 20*14 = 7*20 + 14*x
x = 10 days
View all questions of this test
Most Upvoted Answer
20 men can complete a piece of work in 14 days. 7 men started the work...
Given data:
Number of men required to complete the work = 20
Time taken by 20 men to complete the work = 14 days
7 men started the work and worked for 20 days
After 20 days, 7 more men joined the work

Let's calculate the work done by 7 men in 20 days
Work done by 7 men in 1 day = 1/ (20*20/7) = 7/400
Work done by 7 men in 20 days = (7/400) * 20 = 7/20

Let's calculate the total work done by 7 men in 20 days
Total work done by 7 men in 20 days = (7/20) * 7 = 49/20

Remaining work = 1 - 49/20 = 31/20

Let's calculate the work done by 7 men and 7 more men in 1 day
Work done by 7 men and 7 more men in 1 day = (7+7)/ (20*14) = 1/20

Now, let's calculate the number of days required to complete the remaining work
Let the number of days required to complete the remaining work be x
(7+7) men will work for (20+x) days to complete the remaining work
Work done by (7+7) men in (20+x) days = (7+7) * (1/20) * (20+x) = 14(20+x)/20 = 7(20+x)/10

Total work done by 14 men in (20+x) days = 7/20 + 7(20+x)/10

As per the given data, the total work done by 14 men in (20+x) days should be equal to the remaining work
Therefore, we can equate the above equation to 31/20 and solve for x

7/20 + 7(20+x)/10 = 31/20
7(20+x)/10 = 31/20 - 7/20
7(20+x)/10 = 24/20
20+x = 24*10/7
20+x = 34.2857
x = 34.2857 - 20
x = 14.2857 ≈ 14

Therefore, the remaining work will be completed in 14 days.

Hence, option E is the correct answer.
Free Test
Community Answer
20 men can complete a piece of work in 14 days. 7 men started the work...
Let (7+7) complete remaining work in x days.
So 20*14 = 7*20 + 14*x
x = 10 days
Explore Courses for Quant exam
20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer?
Question Description
20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer?.
Solutions for 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer?, a detailed solution for 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer? has been provided alongside types of 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 20 men can complete a piece of work in 14 days. 7 men started the work and after 20 days, 7 more men joined the work. In how many days the remaining work will be completed?a)18 daysb)20 daysc)8 daysd)12 dayse)10 daysCorrect answer is option 'E'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.