Question Description
A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A, B and C together started work on a task. After completing two-fifths of the work, Cleft while A and B worked together for 24 more days. C then replaced both A and B and completed the remaining work in 12 more days. If C alone takes 30 days to complete the work, in how many days can B alone complete the work? The rate at which A does work is twice the rate at which B does work.a)120b)180c)60d)360e)None of the aboveCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.