Quant Exam  >  Quant Questions  >  2 men or 3 boys can do a piece of work in 14 ... Start Learning for Free
2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?
  • a)
    12 days
  • b)
    14 days
  • c)
    16 days
  • d)
    15 days
  • e)
    10 days
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
2 men or 3 boys can do a piece of work in 14 days working 6 hours each...
B) 14 days Explanation: 2 m = 3 b So 1m = 3/2 b 6m + 8b = 6 * (3/2) b + 9b = 18 b So we have to find the number of days for 18 boys 3 boys do 1 work in 14 days working 6 hours, let 18 boys do twice work in x days working 2 hrs each day, then B1*D1*H1*W2 = B2*D2*H2*W1
3*14*6*2 = 18*x*2*1 Solve x = 14 days
View all questions of this test
Most Upvoted Answer
2 men or 3 boys can do a piece of work in 14 days working 6 hours each...
B) 14 days Explanation: 2 m = 3 b So 1m = 3/2 b 6m + 8b = 6 * (3/2) b + 9b = 18 b So we have to find the number of days for 18 boys 3 boys do 1 work in 14 days working 6 hours, let 18 boys do twice work in x days working 2 hrs each day, then B1*D1*H1*W2 = B2*D2*H2*W1
3*14*6*2 = 18*x*2*1 Solve x = 14 days
Free Test
Community Answer
2 men or 3 boys can do a piece of work in 14 days working 6 hours each...
Given:
2 men or 3 boys can do a piece of work in 14 days working 6 hours each day.

To find:
In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day.

Assumptions:
1. The amount of work done by a man and a boy in one hour is the same.
2. The amount of work done by a man and a boy is directly proportional to the number of hours they work.

Solution:
Let's first calculate the total work done by 2 men or 3 boys in 14 days working 6 hours each day.

Work done by 2 men in one day = (2 men) * (6 hours) = 12 man-hours
Work done by 3 boys in one day = (3 boys) * (6 hours) = 18 boy-hours

Work done by 2 men or 3 boys in 14 days = (12 man-hours + 18 boy-hours) * 14 = 420 man-hours or boy-hours

Now, let's calculate the total work required to be done by 6 men and 9 boys working 2 hours each day.

Total work required = 2 * 420 = 840 man-hours or boy-hours

Let's assume the number of days required to complete the work is x.

Work done by 6 men in one day = (6 men) * (2 hours) = 12 man-hours
Work done by 9 boys in one day = (9 boys) * (2 hours) = 18 boy-hours

Work done by 6 men and 9 boys in x days = (12 man-hours + 18 boy-hours) * x = 30x man-hours or boy-hours

Since the work is twice as large, we can equate the two expressions for work done:

30x = 840

Solving for x, we get:

x = 840 / 30 = 28

Therefore, 6 men and 9 boys will complete the work in 28 days working 2 hours each day.

Since we need to find the answer in terms of days, we round up the number of days to the nearest whole number. Thus, the answer is 28 days.

Therefore, the correct answer is option 'B' (14 days).
Explore Courses for Quant exam
2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer?
Question Description
2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer?.
Solutions for 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 2 men or 3 boys can do a piece of work in 14 days working 6 hours each day. In how many days 6 men and 9 boys will complete a work twice as large working together 2 hours each day?a)12 daysb)14 daysc)16 daysd)15 dayse)10 daysCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev