For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________
    Correct answer is between '29,30'. Can you explain this answer?
    Verified Answer
    For a site consisting of 1m sand layer underlain by 6m clay resting on...
    View all questions of this test
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer?
    Question Description
    For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer?.
    Solutions for For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer?, a detailed solution for For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer? has been provided alongside types of For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For a site consisting of 1m sand layer underlain by 6m clay resting on rock. fill is constructed using this soil is the 50% consolidation of soil takes place in 6.84 years. Then the time required for 90% consolidation of soil is years _______________Correct answer is between '29,30'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev