P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?
  • a)
    10
  • b)
    16
  • c)
    15
  • d)
    20
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
P can do a piece of work in 20 days and Q can do the same piece of wor...
Work done by P in 1 day = 1/20
Work done by Q in 1 day = 1/60
Work done P and Q in 1 day = 1/20 + 1/60 = 1/15
Work done by P and Q in 5 days = 5 ⨯ 1/15 = 1/3
∴ P and Q finished 1/3rd of the work in 5 days.
R finished 2/3rd of the work in 10 days
2/3 work = 10 days
1 work = 10 × (3/2) = 15 days
∴ R will finish the whole work in 15 days.
View all questions of this test
Explore Courses for Railways exam
P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer?
Question Description
P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer?.
Solutions for P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer?, a detailed solution for P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?a)10b)16c)15d)20Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev