Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  The constraints in case of resource smoothing... Start Learning for Free
The constraints in case of resource smoothing operation would be
  • a)
    resources
  • b)
    project duration time
  • c)
    both resources and project duration time
  • d)
    None of the above
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The constraints in case of resource smoothing operation would bea)reso...
(i) Resource Smoothing The total project duration is not changed, but some of the activity start times are shifted by their available floats so that a uniform demand for the resources is generated. The resources are considered to be unlimited.
(ii) Resource levelling The activity start time are so rescheduled that the peak demand for a particular resource does not cross the available limit of the resources. Thus the resources are considered to be limited.
View all questions of this test
Most Upvoted Answer
The constraints in case of resource smoothing operation would bea)reso...
Resource Smoothing Operation Constraints

Resource smoothing is a technique used to balance the demand for resources with the available supply of resources. This technique is used to optimize the utilization of resources in a project while keeping the project duration time as constant as possible. The constraints in case of resource smoothing operation are:

Project Duration Time

The project duration time is the amount of time required to complete the project, from start to finish. The duration of the project is fixed, and it cannot be changed. The resource smoothing operation is performed to ensure that the resources are utilized in the best possible manner, without increasing the project duration time. The project duration time constraint is the most important constraint in resource smoothing operation.

Resources

The resources are the people, materials, and equipment required to complete the project. The resources are limited, and they must be used efficiently to complete the project within the given time frame. The resource smoothing operation is performed to ensure that the resources are utilized in the best possible manner, without overloading any resource. The resource constraint is also an important constraint in resource smoothing operation.

Conclusion

The constraints in case of resource smoothing operation are project duration time and resources. The project duration time is fixed, and it cannot be changed. The resources are limited, and they must be used efficiently to complete the project within the given time frame. The resource smoothing operation is performed to ensure that the resources are utilized in the best possible manner, without overloading any resource.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer?
Question Description
The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The constraints in case of resource smoothing operation would bea)resourcesb)project duration timec)both resources and project duration timed)None of the aboveCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev