The constraints in case of resource smoothing operation would bea)reso...
(i) Resource Smoothing The total project duration is not changed, but some of the activity start times are shifted by their available floats so that a uniform demand for the resources is generated. The resources are considered to be unlimited.
(ii) Resource levelling The activity start time are so rescheduled that the peak demand for a particular resource does not cross the available limit of the resources. Thus the resources are considered to be limited.
View all questions of this test
The constraints in case of resource smoothing operation would bea)reso...
Resource Smoothing Operation Constraints
Resource smoothing is a technique used to balance the demand for resources with the available supply of resources. This technique is used to optimize the utilization of resources in a project while keeping the project duration time as constant as possible. The constraints in case of resource smoothing operation are:
Project Duration Time
The project duration time is the amount of time required to complete the project, from start to finish. The duration of the project is fixed, and it cannot be changed. The resource smoothing operation is performed to ensure that the resources are utilized in the best possible manner, without increasing the project duration time. The project duration time constraint is the most important constraint in resource smoothing operation.
Resources
The resources are the people, materials, and equipment required to complete the project. The resources are limited, and they must be used efficiently to complete the project within the given time frame. The resource smoothing operation is performed to ensure that the resources are utilized in the best possible manner, without overloading any resource. The resource constraint is also an important constraint in resource smoothing operation.
Conclusion
The constraints in case of resource smoothing operation are project duration time and resources. The project duration time is fixed, and it cannot be changed. The resources are limited, and they must be used efficiently to complete the project within the given time frame. The resource smoothing operation is performed to ensure that the resources are utilized in the best possible manner, without overloading any resource.