Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  Consider the following statements:Crashing a ... Start Learning for Free
Consider the following statements:
Crashing a project in terms of its duration would result in
1. an increase in the indirect cost
2. a decrease in the indirect cost
3. a decrease in the direct cost
4. an increase in the direct cost
Which of these statements are correct?
  • a)
    2 and 4
  • b)
    2 and 3
  • c)
    1 and 3
  • d)
    1 and 2
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Consider the following statements:Crashing a project in terms of its d...
Crasing reduces duration and therefore indirect cost decreases while direct cost increase.
View all questions of this test
Most Upvoted Answer
Consider the following statements:Crashing a project in terms of its d...
Crashing a project refers to the process of shortening the project duration by applying additional resources or other measures. When a project is crashed, there are certain impacts on the costs associated with the project. Let's analyze each statement to determine which ones are correct.

1. An increase in the indirect cost:
- The indirect costs of a project are those costs that are not directly related to the physical construction or production of the project deliverables. These costs include overhead expenses, administrative costs, and other miscellaneous expenses.
- When a project is crashed, additional resources may be required, such as overtime pay, expedited shipping, or increased supervision. These additional resources can lead to an increase in indirect costs.
- Therefore, statement 1 is correct.

2. A decrease in the indirect cost:
- As explained above, crashing a project typically leads to an increase in indirect costs. Therefore, statement 2 is incorrect.

3. A decrease in the direct cost:
- The direct costs of a project are those costs that are directly associated with the physical construction or production of the project deliverables. These costs include labor, materials, equipment, and other direct expenses.
- Crashing a project may require additional resources, which can lead to an increase in direct costs. For example, hiring additional workers or renting additional equipment can increase the direct costs.
- Therefore, statement 3 is incorrect.

4. An increase in the direct cost:
- As discussed above, crashing a project usually results in an increase in direct costs due to the need for additional resources. Therefore, statement 4 is correct.

In summary, the correct statements are 2 and 4. Crashing a project can lead to an increase in both indirect costs (statement 1) and direct costs (statement 4), while there is no decrease in either indirect costs (statement 2) or direct costs (statement 3).
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer?
Question Description
Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer?.
Solutions for Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer?, a detailed solution for Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements:Crashing a project in terms of its duration would result in1. an increase in the indirect cost2. a decrease in the indirect cost3. a decrease in the direct cost4. an increase in the direct costWhich of these statements are correct?a)2 and 4b)2 and 3c)1 and 3d)1 and 2Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev