A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?
    Correct answer is '4'. Can you explain this answer?
    Most Upvoted Answer
    A can complete a piece of work in 3 days. B takes double the time take...
    A, B, C and D take 3, 6, 12 and 24 days respectively to complete the work.
    So A, B, C and D complete 33.33%, 16.67%, 8.33% and 4.17% of the work respectively in a day.
    A pair of workers from the 4 can be selected in 6 ways. Each of these pairs and the percentage of work that they finish in a day is as follows:
    A and B: 33.33% + 16.67% = 50%
    A and C: 41.67%
    A and D: 37.5%
    B and C: 25%
    B and D: 20.83%
    C and D: 12.5%
    To complete the work in 4, 3, 2 or 1 day, 25% or 33.33% or 50% or 100% of the work should be completed in a day.
    This can happen if A and B, A and C, A and D or B and C are selected.
    Hence, the pair of workers can be selected in 4 ways.
    Answer: 4
    Free Test
    Community Answer
    A can complete a piece of work in 3 days. B takes double the time take...
    Solution:

    Given, A can complete a task in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task.

    So, B takes 6 days, C takes 12 days and D takes 24 days to complete the same task.

    Let's assume that the contractor selects two workers, X and Y, to complete the task.

    Case 1: X completes the task faster than Y
    There are two possibilities for this case:
    - X = A and Y = B, X = A and Y = C
    In both cases, the total time taken to complete the task is 3 days (A+B) or 6 days (A+C), which is within the given limit of 4 days.

    Case 2: Y completes the task faster than X
    There are two possibilities for this case:
    - X = B and Y = A, X = C and Y = A
    In both cases, the total time taken to complete the task is 6 days (B+A) or 12 days (C+A), which is not within the given limit of 4 days.

    Therefore, there are only 2 possible pairs of workers that can complete the task within 4 days:
    - A and B
    - A and C

    Hence, the correct answer is '4'.
    Explore Courses for CAT exam

    Similar CAT Doubts

    Top Courses for CAT

    A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer?
    Question Description
    A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer? for CAT 2025 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer? covers all topics & solutions for CAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer?.
    Solutions for A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
    Here you can find the meaning of A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer?, a detailed solution for A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer? has been provided alongside types of A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A can complete a piece of work in 3 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. If a contractor wants to complete a task in at most 4 days in how many ways can he select a pair of workers?Correct answer is '4'. Can you explain this answer? tests, examples and also practice CAT tests.
    Explore Courses for CAT exam

    Top Courses for CAT

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev