If the depth is 8.64 cm on a field over a base period of 10 days, then the duty is
  • a)
    10 hectares per cu.m/s
  • b)
    1000 hectares per cu.m/s
  • c)
    100 hectares per cu/m/s
  • d)
    864 hectares per cum/s
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
If the depth is 8.64 cm on a field over a base period of 10 days, then...
Free Test
Community Answer
If the depth is 8.64 cm on a field over a base period of 10 days, then...
Duty Calculation:
The duty of a field is a measure of the amount of water required to irrigate a unit area of land per unit time. It is often expressed in hectares per cubic meter per second (ha/m³/s).

Given:
- Depth of water = 8.64 cm
- Base period = 10 days

To calculate the duty, we need to convert the depth of water into volume and then divide it by the product of the base period and the area of the field.

Step 1: Convert depth to volume:
Depth of water = 8.64 cm = 0.0864 m (1 cm = 0.01 m)
Volume = Area × Depth = 1 m² × 0.0864 m = 0.0864 m³

Step 2: Calculate duty:
Duty = Volume / (Base period × Area)

Since the area is not given in the question, we cannot calculate the exact duty. However, we can determine the duty per unit area.

Step 3: Calculate duty per unit area:
Duty per unit area = Duty / Area

Let's assume the area of the field is 1 hectare (10,000 m²) for simplicity.

Duty per unit area = (0.0864 m³) / (10 days × 10,000 m²)

Now, let's convert the duty per unit area to hectares per cubic meter per second (ha/m³/s):

Duty per unit area = (0.0864 m³) / (10 days × 10,000 m²) × (1 ha / 10,000 m²) × (1 day / 24 hours) × (1 hour / 3600 seconds)

Simplifying the units:

Duty per unit area = (0.0864 m³) / (10 days × 10,000 m²) × (1 ha / 10,000 m²) × (1 day / 24 hours) × (1 hour / 3600 seconds)
= 0.0864 / (10 × 24 × 3600) ha/m³/s
= 0.0001 ha/m³/s

Therefore, the duty per unit area is 0.0001 ha/m³/s or 100 hectares per cubic meter per second (100 ha/m³/s).

Hence, the correct answer is option C: 100 hectares per cu/m/s.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer?
Question Description
If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer?.
Solutions for If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If the depth is 8.64 cm on a field over a base period of 10 days, then the duty isa)10 hectares per cu.m/sb)1000 hectares per cu.m/sc)100 hectares per cu/m/sd)864 hectares per cum/sCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev