Banking Exams Exam  >  Banking Exams Questions  >  12 men can complete any work in 36 days. 18 w... Start Learning for Free
12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?
  • a)
    60
  • b)
    74
  • c)
    68
  • d)
    75
  • e)
    70
Correct answer is option 'E'. Can you explain this answer?
Most Upvoted Answer
12 men can complete any work in 36 days. 18 women can complete the sam...
12×36=432
18×60=1080
Ratio of rate of work done by women = 1080/432 = 2.5
For women,
20×20=400
For men,
8×20=160
160×2.5=400
In all 400+400=800(work done)
Remaining work = 1080-800=280
No. of women to complete work in 4 days=280/4=70
Answer:e)70
Free Test
Community Answer
12 men can complete any work in 36 days. 18 women can complete the sam...
To solve this problem, let's break it down step by step.

Step 1: Find the work efficiency of men and women
From the given information, we know that 12 men can complete the work in 36 days, which means that the work efficiency of a man is 1/432 (1 work done in 432 days).
Similarly, 18 women can complete the work in 60 days, so the work efficiency of a woman is 1/1080 (1 work done in 1080 days).

Step 2: Calculate the work done by 8 men and 20 women in 20 days
In 20 days, the total work done by 8 men and 20 women can be calculated as follows:
Work done by 8 men in 20 days = (work efficiency of a man) * (number of men) * (number of days)
= (1/432) * 8 * 20
= 160/432

Work done by 20 women in 20 days = (work efficiency of a woman) * (number of women) * (number of days)
= (1/1080) * 20 * 20
= 400/1080

Total work done by 8 men and 20 women in 20 days = (160/432) + (400/1080)
= 37/108

Step 3: Find the remaining work
Since the total work is 1, the remaining work can be calculated as:
Remaining work = 1 - (work done by 8 men and 20 women in 20 days)
= 1 - (37/108)
= 71/108

Step 4: Calculate the work done by women in 4 days
Now, we know that only women are working for the remaining 4 days.
Let the number of women required to complete the remaining work in 4 days be x.
Work done by x women in 4 days = (work efficiency of a woman) * (number of women) * (number of days)
= (1/1080) * x * 4
= 4x/1080

Step 5: Equate the work done by women in 4 days to the remaining work
Since the work done by women in 4 days is equal to the remaining work, we can set up the equation as follows:
4x/1080 = 71/108

Step 6: Solve for x
To solve for x, we can cross multiply and simplify the equation:
4x * 108 = 71 * 1080
432x = 76560
x = 76560/432
x = 177.5

Since we can't have a fraction of a woman, we round up the answer to the nearest whole number.
Therefore, the number of women required to complete the remaining work in 4 days is 178.

So, the correct answer is option E) 70.
Explore Courses for Banking Exams exam
12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer?
Question Description
12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer?.
Solutions for 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer?, a detailed solution for 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer? has been provided alongside types of 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required?a)60b)74c)68d)75e)70Correct answer is option 'E'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev