Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?
  • a)
    Rs. 4500
  • b)
    Rs. 3000
  • c)
    Rs. 2000
  • d)
    Rs. 1500
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alo...
⇒ Work done by Rahul in 8 days = 8 × (1/16) = 1/2
⇒ Work done by Ravi in 8 days = 8 × (1/24) = 1/3
It means, Rahul and Ravi done 1/2 and 1/3rd of work, respectively, in 8 days
⇒ Work done by kamlesh = {1 – (1/2 + 1/3)} = 1 – 5/6 = 1/6
⇒ Rahul’s share: Ravi’s share: Kamlesh’sshare = 1/2 : 1/3 : 1/6 = 3 : 2 : 1
⇒ Kamlesh’s share = (1/6) × 9,000 = 1500
∴ Kamlesh’s share is Rs. 1500
View all questions of this test
Explore Courses for Railways exam
Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer?
Question Description
Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer?.
Solutions for Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Rahul and Ravi undertook to do a piece of work for Rs. 9000. Rahul alone could do the work in the 16 days and Ravi in 24 Days. With the assistance Kamlesh, they finished the work in 8 days. How much money should be given to Kamlesh?a)Rs. 4500b)Rs. 3000c)Rs. 2000d)Rs. 1500Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev