X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?
  • a)
    6
  • b)
    3
  • c)
    5
  • d)
    4
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
X can complete a piece of work in 12 days and Y can complete the same ...
Let total work = LCM of 12, 18 = 36
Efficiency of X = 36/12 = 3
Efficiency of Y = 36/18 = 2
5/9th of total work = (5/9)(36) = 20
Together both can complete 20 units of work in 20/(2+3) = 20/5 = 4 days
So the answer is option D.
View all questions of this test
Explore Courses for Railways exam
X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer?
Question Description
X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer?.
Solutions for X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer?, a detailed solution for X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice X can complete a piece of work in 12 days and Y can complete the same work in 18 days, then in how many days will they together complete 5/9th of total work ?a)6b)3c)5d)4Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev