Railways Exam  >  Railways Questions  >  M and N together can complete a job in 4 days... Start Learning for Free
M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Question
  • a)
    8
  • b)
    3
  • c)
    4
  • d)
    6
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
M and N together can complete a job in 4 days, while only N can comple...
Assume total work = LCM of 4 & 6 = 12 units
Efficiency of M&N; = 12/4 = 3
Efficiency of N = 12/6 = 2
Efficiency of M = 3 - 2 = 1
Hence only M can complete 50% of work i,e; 12/2=6 units of work in 6/1 = 6 days
So the answer is option D.
View all questions of this test
Most Upvoted Answer
M and N together can complete a job in 4 days, while only N can comple...
Given Information:
- M and N together can complete a job in 4 days
- N alone can complete the same work in 6 days

Calculating Work Rates:
To calculate the work rates of M and N, we use the formula:
Work Rate = 1 / Time Taken
- Work rate of M and N together = 1/4
- Work rate of N alone = 1/6
Let the work rate of M alone be x.
Therefore, work rate of M and N together = work rate of M alone + work rate of N alone
1/4 = x + 1/6
Solving the above equation, we get:
x = 1/4 - 1/6
x = 1/12
So, the work rate of M alone is 1/12.

Finding the Number of Days:
To find the number of days taken by M alone to complete 50% of the work, we use the formula:
Number of days = Total work / Work Rate
Since M alone completes 1/12 of the work in a day, to complete 50% of the work, M will take:
Number of days = 0.5 / (1/12)
Number of days = 6
Therefore, M alone will take 6 days to complete 50% of the work. Hence, option D is correct.
Explore Courses for Railways exam
M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer?
Question Description
M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer?.
Solutions for M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer?, a detailed solution for M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice M and N together can complete a job in 4 days, while only N can complete the same work in 6 days. Then find the no.of days taken by M alone to complete 50% of the work ?Report Questiona)8b)3c)4d)6Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev