Railways Exam  >  Railways Questions  >  A contractor undertakes to build a wall in 40... Start Learning for Free
A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?
  • a)
    25
  • b)
    30
  • c)
    35
  • d)
    20
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A contractor undertakes to build a wall in 40 days. He employs 50 peop...
According to the given information, 50 men completed 0.4 work in 20 days and (M + 50) men should complete the remaining 1 – 0.4 = 0.6 work in remaining time i.e. 40 – 20 = 20 
View all questions of this test
Most Upvoted Answer
A contractor undertakes to build a wall in 40 days. He employs 50 peop...
Given:
- A contractor undertakes to build a wall in 40 days.
- He employs 50 people for the same.
- After 20 days, only 40% of the work is completed.

To find:
- How many more men need to be employed to complete the work in time.

Solution:
Let's assume that the total work required to build the wall is 100 units.
- So, 40% of the work completed in 20 days = 40 units
- Remaining work = 100 - 40 = 60 units
- Time left to complete the work = 40 - 20 = 20 days

Now, let's calculate the rate of work done by each person in a day (assuming that each person has the same efficiency):
- Total men employed = 50
- Work done by each person in a day = 100/ (50*40) = 1/200 units
- Work done by each person in 20 days = (1/200)*20 = 1/10 units

So, in 20 days, the work done by 50 men = (1/10)*50 = 5 units

Remaining work = 60 units
Work to be done in 20 days = 60 - 5 = 55 units

Now, let's calculate the number of men required to complete 55 units of work in 20 days:
- Work to be done by each person in a day = 55/(x*20), where x is the number of men required
- Work done by each person in a day = 1/200 units
- So, 55/(x*20) = 1/200
- Solving this equation, we get x = 75

Therefore, the number of men needed to complete the work in time = 75 - 50 = 25

Hence, option A is the correct answer.
Explore Courses for Railways exam
A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer?
Question Description
A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer?.
Solutions for A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer?, a detailed solution for A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contractor undertakes to build a wall in 40 days. He employs 50 people for the same. However, after 20 days he finds that only 40% of the work is completed. How many more man need to be employed to complete the work in time?a)25b)30c)35d)20Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev