Group Question
Answer the following question based on the information given below.
The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.
If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?
    Correct answer is '192'. Can you explain this answer?
    Verified Answer
    Group QuestionAnswer the following question based on the information g...

     
    All the activities are plotted in the Gantt chart shown above.
    The number written beside each activity represents the number of man power required for that activity.
    Calculation of man power requirement on any given day is done as follows:
    Consider as an example Day 6; the activities which would be in progress on Day 6 would be B, C, F and N. Hence, the total man power required for Day 6 would be 15.
    The minimum time that would be required to execute the project completely is 24 days, as is evident from graph above.
    Total hours required would be 24 x 8 = 192 hours
    Answer: 192
    This question is part of UPSC exam. View all CAT courses
    Explore Courses for CAT exam

    Top Courses for CAT

    Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer?
    Question Description
    Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer?.
    Solutions for Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
    Here you can find the meaning of Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer?, a detailed solution for Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer? has been provided alongside types of Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Group QuestionAnswer the following question based on the information given below.The table below shows the series of activities that are required to complete a particular project. The dependent activities can start only when the activity/activities on which they are dependent on is/are completed.If the project has to be completed in the minimum possible duration, then how many hours would be required to complete the project assuming 8 working hours in a day?Correct answer is '192'. Can you explain this answer? tests, examples and also practice CAT tests.
    Explore Courses for CAT exam

    Top Courses for CAT

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev