The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.
Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?
  • a)
    0.9
  • b)
    0.7
  • c)
    0.6
  • d)
    0.3
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The table below shows the estimated cost (in Rs. Lakh) of a project of...
The estimated costs of material and labour for different years are :
⇒ 1988 = 2.1 1989 = 95+70+15+25+25 = 230
⇒ 1990 = 80+45+12+18+20 = 175
⇒ 1991 = 75+60+16+21+18 = 190
The proportion of these expenditures till 1990 = (2.1 + 230 + 175) / (2.1 + 230 + 175 + 190) = 0.6817.
View all questions of this test
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer?
Question Description
The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer?.
Solutions for The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer?, a detailed solution for The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places.Q. If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev