Directions: Study the given information and answer the following question.
The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.
Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?
  • a)
    0.9
  • b)
    0.7
  • c)
    0.6
  • d)
    0.3
  • e)
    0.5
Correct answer is option 'B'. Can you explain this answer?
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer?
Question Description
Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer?.
Solutions for Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Directions: Study the given information and answer the following question.The table given below shows the estimated cost (in Rs. lakh) of a project of laying a railway line between two places, the project began in 1988 and was completed in 1991.Q. If the length of line to be laid each year was in proportion to the estimated cost for material and labour, what fraction of the total length was proposed to be completed by the third year?a)0.9b)0.7c)0.6d)0.3e)0.5Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev