Defence Exam  >  Defence Questions  >  The critical path of the PERT chart is thea)A... Start Learning for Free
The critical path of the PERT chart is the
  • a)
    A path which takes the shortest time to complete the project
  • b)
    A path which takes the longest time to complete the project
  • c)
    The shortest material route
  • d)
    The longest material route
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The critical path of the PERT chart is thea)A path which takes the sho...
The minimum time to complete the project is the maximum of all paths from start to finish. So a critical path is the longest path in the network. 
View all questions of this test
Explore Courses for Defence exam
The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer?
Question Description
The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer? for Defence 2024 is part of Defence preparation. The Question and answers have been prepared according to the Defence exam syllabus. Information about The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Defence 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Defence. Download more important topics, notes, lectures and mock test series for Defence Exam by signing up for free.
Here you can find the meaning of The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The critical path of the PERT chart is thea)A path which takes the shortest time to complete the projectb)A path which takes the longest time to complete the projectc)The shortest material routed)The longest material routeCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Defence tests.
Explore Courses for Defence exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev