A project consist of following activities
Minimum time required to complete the project in (days) is __________
  • a)
    23
  • b)
    23
Correct answer is between ' 23, 23'. Can you explain this answer?
Verified Answer
A project consist of following activitiesMinimum time required to com...
A‐ D‐ G = 4 + 5 + 8 = 17
A‐C‐E‐G = 4 + 6 + 5 + 8 = 23
B‐ E‐ G = 6 + 5 + 8 = 19
B‐ F = 6 + 6 = 12
A‐ C‐ F = 4 + 6 + 6 = 16
View all questions of this test
Most Upvoted Answer
A project consist of following activitiesMinimum time required to com...
A‐ D‐ G = 4 + 5 + 8 = 17
A‐C‐E‐G = 4 + 6 + 5 + 8 = 23
B‐ E‐ G = 6 + 5 + 8 = 19
B‐ F = 6 + 6 = 12
A‐ C‐ F = 4 + 6 + 6 = 16
Explore Courses for Mechanical Engineering exam
Question Description
A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer?.
Solutions for A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer?, a detailed solution for A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer? has been provided alongside types of A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A project consist of following activitiesMinimum time required to complete the project in (days) is __________a) 23b) 23Correct answer is between ' 23, 23'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam
Signup to solve all Doubts
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev