Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   In CPM network critical path denotes thea) p... Start Learning for Free
In CPM network critical path denotes the
  • a)
    path where maximum resources are used
  • b)
    path where minimum resources are used
  • c)
    path where delay of one activity prolongs the duration of completion of project
  • d)
    path that gets monitored automatically
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
In CPM network critical path denotes thea) path where maximum resourc...
Total float in critical path is zero so delay in any activity will delay project.
View all questions of this test
Most Upvoted Answer
In CPM network critical path denotes thea) path where maximum resourc...
Explanation:
CPM (Critical Path Method) is a project management technique used to determine the critical path in a project. The critical path is the sequence of activities that determines the earliest possible completion of the project. It is the longest path through the network and has zero float.

The correct answer is option 'C', i.e., the path where the delay of one activity prolongs the duration of completion of the project. Let's understand why this is the correct answer by looking at the following points:

1. Definition of critical path: As mentioned earlier, the critical path is the longest path through the network and has zero float. It is the sequence of activities that determines the earliest possible completion of the project.

2. Activities on the critical path: The activities on the critical path are those that have no slack or float. Any delay in these activities will delay the completion of the project.

3. Impact of delay on critical path: Delay in any activity on the critical path will increase the duration of the project. This is because the activities on the critical path are dependent on each other, and any delay in one activity will delay the subsequent activities.

4. Importance of critical path: The critical path is essential for project management as it helps in identifying the activities that need to be completed on time to ensure the timely completion of the project. It also helps in identifying the activities that can be delayed without affecting the project duration.

In conclusion, the critical path in a CPM network is the path where the delay of one activity prolongs the duration of completion of the project. It is an essential concept in project management and helps in identifying the activities that need to be completed on time to ensure the timely completion of the project.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer?
Question Description
In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer?.
Solutions for In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In CPM network critical path denotes thea) path where maximum resources are usedb) path where minimum resources are usedc) path where delay of one activity prolongs the duration of completion of projectd) path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev