For an activity of duration 8 days in a network,
Total float = 10 days
Free float = 4 days
Independent float = 0
Then find no. of days an activity can be delayed without effecting project completion time is
    Correct answer is '10'. Can you explain this answer?
    Verified Answer
    For an activity of duration 8 days in a network,Total float = 10 daysF...
    Total float is the time by which an activity can be delayed without delaying the project completion date. Thus, it is the extra time available for an activity.
    In this case, total float = 10 days,
    So, an activity can be delayed by 10 days.
    View all questions of this test
    Most Upvoted Answer
    For an activity of duration 8 days in a network,Total float = 10 daysF...
    Activity Duration and Float
    In project management, the duration of an activity refers to the time it takes to complete that particular task. Float, on the other hand, refers to the amount of time an activity can be delayed without affecting the project's overall completion time. There are different types of float, including total float, free float, and independent float.

    Total Float
    Total float is the maximum amount of time an activity can be delayed without delaying the project's completion time. It is calculated by subtracting the activity duration from the project's critical path duration. The critical path is the longest sequence of dependent activities that determines the project's overall duration.

    Free Float
    Free float is the amount of time an activity can be delayed without delaying the early start of any successor activity. In other words, it represents the flexibility in scheduling non-critical activities. Free float is calculated by subtracting the activity duration from the earliest finish time of all its dependent activities.

    Independent Float
    Independent float is the amount of time an activity can be delayed without delaying any other activity, including its dependent activities. It represents the maximum amount of time an activity can be delayed without impacting the project's schedule.

    Calculation
    In this given scenario, the activity has a duration of 8 days. The total float is 10 days, the free float is 4 days, and the independent float is 0 days.

    Since the total float is 10 days, it means that the activity can be delayed by up to 10 days without delaying the project's completion time. This is because there is enough flexibility in the schedule to accommodate the delay.

    However, it is important to note that delaying an activity by the full float duration is not always recommended. It is generally advisable to minimize the use of float and keep the project on track as much as possible.

    In summary, the given activity can be delayed by up to 10 days without affecting the project completion time.
    Attention Mechanical Engineering Students!
    To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer?
    Question Description
    For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer?.
    Solutions for For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
    Here you can find the meaning of For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer?, a detailed solution for For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer? has been provided alongside types of For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For an activity of duration 8 days in a network,Total float = 10 daysFree float = 4 daysIndependent float = 0Then find no. of days an activity can be delayed without effecting project completion time isCorrect answer is '10'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev