A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition is
  • a)
    0.64 m
  • b)
    0.54 m
  • c)
    0.44 m
  • d)
    0.34 m
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A hump is to be provided on the channel bed. The maximum height of th...
View all questions of this test
Most Upvoted Answer
A hump is to be provided on the channel bed. The maximum height of th...
Explanation:

The provision of hump on the channel bed is done to increase the flow depth and velocity of water. This is done in order to reduce sediment deposition in the channel bed and to maintain the required flow conditions.

The maximum height of the hump should not affect the upstream flow condition. This means that the water flow should not back up or create any disturbance in the upstream flow condition.

The maximum height of the hump can be calculated using the following formula:

h = (v^2 / 2g) + y

Where,
h = height of the hump
v = velocity of flow
g = acceleration due to gravity
y = depth of flow

The value of y should be equal to the normal depth of flow before the hump is provided.

As per the given options, the maximum height of the hump should be less than or equal to 0.54 m. This is calculated using the above formula.

Therefore, option B is the correct answer.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer?
Question Description
A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A hump is to be provided on the channel bed. The maximum height of the hump without affecting the upstream flow condition isa) 0.64 mb) 0.54 mc) 0.44 md) 0.34 mCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev