CAT Exam  >  CAT Questions  >  DIRECTIONSfor the question:Solve the followin... Start Learning for Free
DIRECTIONS for the question: Solve the following question and mark the best possible option.
A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?
  • a)
    360 days
  • b)
    90 days
  • c)
    150 days
  • d)
    180 days
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
DIRECTIONSfor the question:Solve the following question and mark the b...
►Let the units of work done by A, B and C in a single day be a, b and c respectively.
►We know that 90 (a + b) = 120 (a + c)
►Solving we get,  a + 4c = 3b  ----   (1)
►Also, 80 (a + c) + 40 b =  120 (a + c)
►So 40 (a + c) = 40 b
►Or a + c =  b     -----------   (2)
►Solving equation (1) and  (2) together,
►we get
3b - 4c = b - c
=> 2b =  3c
=> b = 3/2 c
=> a = 1/2 c
►Now, total work done = 90 (a + b) = 90 (3c/2 + c/2 ) = 90 (2c) = 180 c
So, working alone C will take 180 c / c = 180 days
View all questions of this test
Most Upvoted Answer
DIRECTIONSfor the question:Solve the following question and mark the b...
To solve this question, we can use the concept of work done per day. Let's denote the work done by A, B, and C per day as x, y, and z respectively.

1. Working together:
Given that A and B can complete the work in 90 days, we can write the equation:
(A's work per day + B's work per day) x (number of days) = total work
(x + y) x 90 = 1
=> x + y = 1/90

2. A and C working together:
Given that A and C can complete the work in 120 days, we can write the equation:
(A's work per day + C's work per day) x (number of days) = total work
(x + z) x 120 = 1
=> x + z = 1/120

3. A, B, and C working together:
Given that A, B, and C complete the work in 80 days when A and C work on all 80 days and B works on every alternate day, we can write the equation:
(A's work per day + B's work per day + C's work per day) x (number of days) = total work
(x + y/2 + z) x 80 = 1
=> 2x + y + 2z = 1/80
=> 2x + 2z = 1/80 - y/80
=> 2(x + z) = 1/80 - y/80
=> x + z = 1/160 - y/160
=> x + z = (1 - y)/160

Comparing equations 2 and 3, we get:
1/120 = (1 - y)/160
=> 160 = 120(1 - y)
=> 160 = 120 - 120y
=> 40 = -120y
=> y = -1/3

Substituting the value of y in equation 1, we get:
x + (-1/3) = 1/90
=> x = 1/90 + 1/3
=> x = 11/90

Now, we can find the time taken by C alone to complete the work:
C's work per day = z = 1 - (x + y)
=> z = 1 - (11/90 + (-1/3))
=> z = 1 - (11/90 - 30/90)
=> z = 1 - (-19/90)
=> z = 1 + 19/90
=> z = 109/90

Therefore, C alone would take 90/109 days to complete the work, which is approximately 0.826 days. Rounding it off, C alone would take 1 day to complete the work.

Hence, the correct answer is option 'D' - 180 days.
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

There are 4 properties available for rent in the city of Hyderabad. They are in 4 different locations among Kondapur, Madhapur, Whitefield and Gachibowli. The rents of the 4 properties are 20000 Rs/month, 24000 Rs/month, 28000 Rs/month and 30000 Rs/month in no particular order. The security deposits of the 4 properties are 1 month equivalent of rent, 2 months equivalent of rent, 3 months equivalent of rent and 4 months equivalent of rent, in no particular order. Also, there are 4 different brokers A, B, C, D who have the responsibility to rent these 4 properties. Brokers belong to 3 categories, truth-tellers, who always tell the truth, liars who always lie and alternators, who alternate between truth and a lie. It is also known that at least one of the brokers is a truth-teller. Also, each of them says 3 statements each, recorded as follows:A:1. The highest amount of rent is for the Gachibowli property.2. The lowest amount of rent is not for the Kondapur property.3. The broker, D sometimes lies.B:1. The Kondapur property has a deposit equivalent to 4 months of rent.2. The broker, C never speaks the truth.3. The rent of Whitefield is 24000 Rs/month.C:1. The rent of the Whitefield property(in Rs) when divided by 1000 has 8 distinct factors.2. The broker, A never speaks the truth.3. The monthly rent of the Whitefield property is neither the highest nor the lowest.D:1. The average of all rents is 25500 Rs/month.2. The broker, A is not an alternator.3. The Madhapurproperty has a deposit equivalent to 3 months of rent.Based on the information given above, answer the questions that follow.Q. Which of the following is a correct match?

DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice DIRECTIONSfor the question:Solve the following question and mark the best possible option.A, B and C complete a particular work in 80 days when A and C worked on all 80 days, whereas B worked on every alternate day. A and B can together complete the work in 90 days and A and C in 120 days. In how many days would C alone take to complete the work?a)360 daysb)90 daysc)150 daysd)180 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev