CAT Exam  >  CAT Questions  >  DIRECTIONS for the question: Network Systems ... Start Learning for Free
DIRECTIONS for the question:
Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.
The table below gives the descriptions of the times taken to complete each of these activities.

Q. IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?
I. Reduce the time spent in designing hardware by 3 weeks.
II. Reduce the time spent in finishing the manual by 3 weeks.
III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.
  • a)
    I or II
  • b)
    I or III
  • c)
    II or III
  • d)
    I or II or III
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
DIRECTIONS for the question: Network Systems Ltd. has just taken on a ...
Path 1: 1-2-3-5-6-7-11.
Time: 6+4+2+3+2+4 = 21 weeks.
Path 2: 1-2-3-5-6-8-11.
Time: 6+4+2+3+4+1 = 20 weeks.
Path 3: 1-2-6-8-11.
Time: 6+6+4+1 = 17 weeks.
Path 4: 1-2-4-9-10-11.
Time: 6+3+4+1+4 = 18 weeks.
Path 5: 1-2-6-7-11.
Time : 6+6+2+4 = 18 weeks.
If the time spent in designing hardware (activity 2 – 3) is reduced by 3 weeks, then the times for paths 1 to 5 from node 1 to node 11 become 18 weeks, 17 weeks, 17 weeks, 18 weeks and 18 weeks respectively. So they will be able to deliver in 18 weeks.
If the time spent in finishing the manual (activity 4 – 9) is reduced by 3 weeks, then the times for paths 1 to 5 from node 1 to node 11 are 21 weeks, 20 weeks, 17 weeks, 15 weeks and 18 weeks respectively. Since there are paths that take longer than 18 weeks, they will not be able to deliver in 18 weeks.
If the time spent in formalizing specifications (activity 1 – 2) is reduced by 2 weeks and the time spent in testing hardware (activity 5 – 6) is reduced by 1 week, then the times for paths 1 to 5 from node 1 to node 11 are 18 weeks, 17 weeks, 15 weeks, 16 weeks and 16 weeks respectively. So they will be able to deliver in 18 weeks.
Therefore, they should implement options I or III.
View all questions of this test
Explore Courses for CAT exam
DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer?
Question Description
DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer?.
Solutions for DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer?, a detailed solution for DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice DIRECTIONS for the question: Network Systems Ltd. has just taken on a new project for their client IPL Logistics Ltd. The following network diagram shows the sequence of activities involved in the completion of the project. The project starts at node 1 and is completed at node 11. Activities can happen simultaneously. However, an activity cannot be started unless all prior activities have been completed, e.g., the activities at node 6 cannot start unless all activities at nodes 1, 2, 3 and 5 have been completed.The table below gives the descriptions of the times taken to complete each of these activities.Q.IPL Logistics Ltd. insists that the project be delivered in 18 weeks. Which of the following options should Network Systems Ltd. implement so that they can deliver the project on time?I. Reduce the time spent in designing hardware by 3 weeks.II. Reduce the time spent in finishing the manual by 3 weeks.III. Reduce the time spent in formalizing specifications by 2 weeks and in testing hardware by 1 week.a)I or IIb)I or IIIc)II or IIId)I or II or IIICorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev