CAT Exam  >  CAT Questions  >  A can do some work in 24 days, B can do it in... Start Learning for Free
A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20?
Most Upvoted Answer
A can do some work in 24 days, B can do it in 32 days and C can do it ...
Solution:

Given, A can do the work in 24 days, B can do it in 32 days, and C can do it in 60 days.
Let the total work be 240 units.
Let the efficiency of A, B, and C be a, b, and c respectively.
Then, a = 240/24 = 10 units/day
b = 240/32 = 7.5 units/day
c = 240/60 = 4 units/day

Calculation of work done by A, B, and C in 6 and 8 days

Let x be the number of days taken to complete the work.
Let A work for 6 days and B work for 8 days.
Total work done by A and B in 6 days = 6a + 8b = 6(10) + 8(7.5) = 90 units
Remaining work = 240 - 90 = 150 units
Total work done by A, B, and C in x days = xa + (x-6)b + (x-14)c
= x(10) + (x-6)(7.5) + (x-14)(4)
= 10x + 7.5x - 45 + 4x - 56
= 21.5x - 101

Calculation of remaining work

As per the given question, A left after 6 days and B left after 8 days. Therefore, the remaining work is done by C.
Work done by C in (x-14) days = (x-14)c = (x-14)(4) units

Calculation of total work done

Total work done = Work done by A + Work done by B + Work done by C
= 6a + 8b + (x-14)c
= 60 + 60 + 4x - 56
= 4x + 4

Calculation of x

Total work done = 240 units
4x + 4 = 240
4x = 236
x = 59

Therefore, the whole work will be completed in 59 days.
Answer: Option A (35) is incorrect. Option B (30) is incorrect. Option C (22) is incorrect. Option D (20) is incorrect.
Community Answer
A can do some work in 24 days, B can do it in 32 days and C can do it ...
C 22
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20?
Question Description
A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20?.
Solutions for A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20? defined & explained in the simplest way possible. Besides giving the explanation of A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20?, a detailed solution for A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20? has been provided alongside types of A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20? theory, EduRev gives you an ample number of questions to practice A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work? A.35 B.30 C.22 D.20? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev