Which one of the following is carried out by two theodolite method?
  • a)
    Circular curve ranging
  • b)
    Tacheometric survey
  • c)
    Geodetic survey
  • d)
    Astronomical survey
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
Which one of the following is carried out by two theodolite method?a)C...
Circular Curve Ranging using Two Theodolite Method

Circular curve ranging is a process of determining the position of points on a curve with respect to a given reference line. Two theodolite method is a common technique used to carry out circular curve ranging. This method involves the use of two theodolites placed at two stations on the reference line.

Steps involved in circular curve ranging using two theodolite method:

1. Setting up the theodolites: Two theodolites are set up at two stations on the reference line. The distance between the two stations should be at least equal to the radius of the curve.

2. Taking readings: The theodolites are used to take readings of the angles between the reference line and the tangent at each point on the curve. The readings are taken from both the stations.

3. Calculating the position of points on the curve: The angles measured at each point on the curve are used to calculate the position of the point with respect to the reference line. This calculation involves trigonometry and geometry.

4. Plotting the curve: The points calculated in the previous step are plotted on a graph to obtain the curve.

Advantages of two theodolite method:

1. It is a simple and accurate method of circular curve ranging.

2. It can be used in areas with difficult terrain.

3. It is relatively inexpensive compared to other methods.

Disadvantages of two theodolite method:

1. It requires skilled personnel to operate the instruments.

2. It is time-consuming and may take longer to complete compared to other methods.

Conclusion:

Circular curve ranging using two theodolite method is a useful technique in civil engineering for determining the position of points on a curve with respect to a reference line. It is a simple and accurate method that can be used in a variety of situations. However, it does require skilled personnel to operate the instruments and can be time-consuming.
Free Test
Community Answer
Which one of the following is carried out by two theodolite method?a)C...
Because of , basically Circular Curve Ranging carried out by two theodolite method, else where the given option are not suitable for the same, so that option-A is correct..
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer?
Question Description
Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which one of the following is carried out by two theodolite method?a)Circular curve rangingb)Tacheometric surveyc)Geodetic surveyd)Astronomical surveyCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev