The following are the instrumental methods used for setting out horizontal circular curve.
(i) Rankine's method of tangential angle
(ii) Two theodolite method
(iii) Tacheometric method
The sequence of these methods from the least accurate to the most accurate is
  • a)
    (i), (ii), (iii)
  • b)
    (iii), (i), (ii)
  • c)
    (ii), (iii), (i)
  • d)
    (i), (iii), (ii)
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
The following are the instrumental methods used for setting out horizo...
Angular methods
The following are the angular methods that can be used for setting circular curves:
  • Rankine method of tangential (deflection) angles.
  • Two-theodolite method
  • Tacheometric method
Rankine Method of tangential angles:
  • Rankine method is based on the principle that the deflection angle to any point on a circular curve is measured by one half the angle subtended by the arc from Point of curve to that point.
  • The method is most accurate since each point is fixed independently.
Two theodolite method: 
  • This method is used when the ground is unsuitable for chaining and is based on the principle that the angle between the tangent and the chord is equal to the angle which that chord subtends in the opposite segment.
Tacheometric method: 
  • this method is less accurate than “Rankine Method of tangential angles”.
Free Test
Community Answer
The following are the instrumental methods used for setting out horizo...
Explanation:

The instrumental methods used for setting out horizontal circular curves are Rankine's method of tangential angle, two theodolite method, and tacheometric method. These methods vary in terms of accuracy.

(i) Rankine's method of tangential angle:
- Rankine's method of tangential angle is the simplest method for setting out horizontal circular curves.
- In this method, the tangential angle is measured between the tangent to the curve at the P.C. and the tangent to the curve at the P.T.
- This method is the least accurate among the three methods mentioned.
- It is suitable for small curves or where high accuracy is not required.

(ii) Two theodolite method:
- The two theodolite method is a more accurate method for setting out horizontal circular curves.
- In this method, two theodolites are set up at the P.C. and P.T. stations.
- The angles are measured from both the theodolites to the tangent to the curve at a known point.
- By using the measured angles, the coordinates of the center of the curve can be calculated.
- This method is more accurate than Rankine's method but less accurate than the tacheometric method.

(iii) Tacheometric method:
- The tacheometric method is the most accurate method for setting out horizontal circular curves.
- In this method, a tacheometer is used to measure the vertical angles and the distances.
- The tacheometer is set up at the P.C. station, and the angles and distances are measured to the tangent to the curve at a known point.
- By using the measured angles and distances, the coordinates of the center of the curve can be calculated.
- This method provides the highest accuracy among the three methods mentioned.

Sequence of methods:
- The question asks for the sequence of these methods from the least accurate to the most accurate.
- Based on the explanations given above, the correct sequence is (ii), (iii), (i).
- Therefore, option 'C' is the correct answer.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer?
Question Description
The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer?.
Solutions for The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer?, a detailed solution for The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The following are the instrumental methods used for setting out horizontal circular curve.(i) Rankines method of tangential angle(ii) Two theodolite method(iii) Tacheometric methodThe sequence of these methods from the least accurate to the most accurate isa)(i), (ii), (iii)b)(iii), (i), (ii)c)(ii), (iii), (i)d)(i), (iii), (ii)Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev