CAT Exam  >  CAT Questions  >  A contractor agreed to construct a 6 km road ... Start Learning for Free
A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time? 
    Correct answer is '40'. Can you explain this answer?
    Verified Answer
    A contractor agreed to construct a 6 km road in 200 days. He employed ...

    Additional men required = 180 - 140 = 40
    View all questions of this test
    Most Upvoted Answer
    A contractor agreed to construct a 6 km road in 200 days. He employed ...
    Given Information:
    - Length of road to be constructed = 6 km
    - Total time given to complete the road = 200 days
    - Number of persons employed initially = 140
    - Length of road completed in 60 days = 1.5 km

    Approach:
    To find the number of additional people needed to finish the work on time, we need to calculate the work done by the current workforce and then determine the additional workforce required to complete the remaining work within the given time frame.

    Calculating Work Done:
    - The total work to be done is constructing a 6 km road.
    - In the first 60 days, only 1.5 km of road has been completed.
    - Therefore, the work done in 60 days = 1.5 km.

    Calculating Work Remaining:
    - The remaining work can be calculated as the difference between the total work and the work done in 60 days.
    - Remaining work = Total work - Work done in 60 days
    - Remaining work = 6 km - 1.5 km = 4.5 km.

    Calculating Work Done by Each Person:
    - To calculate the number of additional people needed, we need to determine the work done by each person in the first 60 days.
    - Work done by each person in 60 days = Work done / Number of persons employed initially
    - Work done by each person in 60 days = 1.5 km / 140 persons.

    Calculating Work Done by Each Person per Day:
    - Since the work done by each person is calculated for 60 days, we need to find the work done by each person per day.
    - Work done by each person per day = Work done by each person in 60 days / 60 days.
    - Work done by each person per day = (1.5 km / 140 persons) / 60 days.

    Calculating Total Work Done:
    - Now, we need to calculate the total work done by all the people for the remaining 140 days.
    - Total work done = Work done by each person per day * Number of persons * Remaining days
    - Total work done = (1.5 km / 140 persons) / 60 days * 140 persons * 140 days.

    Calculating Additional Workforce:
    - To find the number of additional people needed to finish the work on time, we need to calculate the work remaining after 140 days and divide it by the work done by each person per day.
    - Additional workforce needed = Remaining work / (Work done by each person per day * Remaining days)
    - Additional workforce needed = 4.5 km / ((1.5 km / 140 persons) / 60 days * 140 persons * 140 days).

    Simplifying the Equation:
    - Simplifying the above equation will give us the number of additional people needed.
    - Additional workforce needed = 40.

    Therefore, the contractor would need to employ an additional 40 people to finish the work exactly on time.
    Attention CAT Students!
    To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
    Explore Courses for CAT exam

    Similar CAT Doubts

    A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer?
    Question Description
    A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer?.
    Solutions for A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
    Here you can find the meaning of A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer?, a detailed solution for A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer? has been provided alongside types of A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?Correct answer is '40'. Can you explain this answer? tests, examples and also practice CAT tests.
    Explore Courses for CAT exam

    Top Courses for CAT

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev