A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A builder decided to construct a fly-over in 42 months. Initially he had employed 150 men, but after 25 months he realized that the deadline couldn't be met, and hence he employed 60 more men and completed the construction 2 months before the stipulated time. If he had not employed the additional men, how many months behind the schedule would the construction have been finished?a)4 monthsb)6 monthsc)8 monthsd)10 monthsCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.