6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?
  • a)
    6 women
  • b)
    9 women
  • c)
    8 women
  • d)
    24 women
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
6 men can complete a certain piece of work in 4 days, whereas 8 women...
1man′s 1day′s work =1 / 24
1 woman's 1 day's work = 1 / 32
3 men's 2 days' work = 6 / 24 = 14
Remaining work = 1 − 1 / 4 = 34
1 / 32 of the work is done by 1 woman in 1 day.
Or, total work can be done by 3/2 women in 1 day. Therefore, 3/4 of the work shall be done by
3 / 4 × 32 = 24 women in 1 day, or 8 women in 3 days 8 × 3 = 24
Attention CLAT Students!
To make sure you are not studying endlessly, EduRev has designed CLAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CLAT.
Explore Courses for CLAT exam

Top Courses for CLAT

6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer?
Question Description
6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? for CLAT 2024 is part of CLAT preparation. The Question and answers have been prepared according to the CLAT exam syllabus. Information about 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for CLAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer?.
Solutions for 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for CLAT. Download more important topics, notes, lectures and mock test series for CLAT Exam by signing up for free.
Here you can find the meaning of 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice CLAT tests.
Explore Courses for CLAT exam

Top Courses for CLAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev