6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?
  • a)
    6 women
  • b)
    9 women
  • c)
    8 women
  • d)
    24 women
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
6 men can complete a certain piece of work in 4 days, whereas 8 women...
1man′s 1day′s work =1 / 24
1 woman's 1 day's work = 1 / 32
3 men's 2 days' work = 6 / 24 = 14
Remaining work = 1 − 1 / 4 = 34
1 / 32 of the work is done by 1 woman in 1 day.
Or, total work can be done by 3/2 women in 1 day. Therefore, 3/4 of the work shall be done by
3 / 4 × 32 = 24 women in 1 day, or 8 women in 3 days 8 × 3 = 24
Free Test
Community Answer
6 men can complete a certain piece of work in 4 days, whereas 8 women...
Understanding the Problem
To solve the problem, we first need to determine the work rate of men and women.
Work Rates
- 6 men can complete the work in 4 days.
- Therefore, 1 man can complete the work in 6 times 4 days = 24 days.
- Work done by 1 man in 1 day = 1/24.
- 8 women can complete the same work in 4 days.
- Therefore, 1 woman can complete the work in 8 times 4 days = 32 days.
- Work done by 1 woman in 1 day = 1/32.
Work Done by Men in 2 Days
- 3 men work for 2 days:
- Work done by 3 men in 1 day = 3 * (1/24) = 1/8.
- Work done by 3 men in 2 days = 2 * (1/8) = 1/4.
Remaining Work
- Total work = 1 (whole work).
- Work done by 3 men = 1/4.
- Remaining work = 1 - 1/4 = 3/4.
Time and Work Calculation
- Remaining work = 3/4 needs to be completed in 3 days.
- Work needed per day = (3/4) / 3 = 1/4.
Women Needed to Complete the Work
- Work done by 1 woman in 1 day = 1/32.
- Let 'x' be the number of women required to complete 1/4 work in 1 day:
- x * (1/32) = 1/4.
- x = (1/4) / (1/32) = 8.
Thus, the number of women required to complete the remaining work in the given time is 8.
Final Answer
The correct option is c) 8 women.
Explore Courses for CLAT exam

Similar CLAT Doubts

Direction: You have been given some passages followed by questions based on each passage. You are required to choose the most appropriate option which follows from the passage. Only the information given in the passage should be used for choosing the answer and no external knowledge of law howsoever prominent is to be applied.Vicarious liability has been considered by Englands highest courts in a flood of cases in recent years and the law has taken another step forward with judgments from the Supreme Court; Originally, the doctrine of vicarious liability was confined to cases where a wrongdoer was employed by a defendant.It was later recognised that a relationship can give rise to vicarious liability even in the absence of a contract of employment, e.g., where an employer lends his employee to a third party, the third party may be treated as the employerfor vicarious liability purposes.In the Christian Brothers Case, the Court considered the general approach in deciding whether a relationship other than one of employment can give rise to vicarious liability, subject to there being a sufficient connection between that relationship and the tort in question and extended the scope of the doctrine.That case concerned whether the defendant, an international unincorporated association whose mission was to provide children with a Christian education, was vicariously liable for the sexual abuse of children by members of the institute, otherwise known as brothers, who taught at an approved school. The Supreme Court held that it was.Lord Phillips stated that: "The relationship that gives rise to vicarious liability is in the vast majority of cases that of employer and employee under a contract of employment. The employer will be vicariously liable when the employee commits a tort in the course of his employment. There is no difficulty in identifying a number of policy reasons that usually make it fair, just and reasonable to impose vicarious liability on the employer when these criteria are satisfied:1. The employer is more likely to have the means to compensate the victim than the employee and can be expected to have insured against that liability;2. The tort will have been committed as a result of activity being taken by the employee on behalf of the employer;3. The employees activity is likely to be part of the business activity of the employer;4. The employee will, to a greater or lesser degree, have been under the control of the employer."He added that: "Where the defendant and tortfeasor are not bound by a contract of employment, but their relationship has the same incidents, that relationship can give rise to vicarious liability on the ground that its akin to that between an employer and an employee."Which of the following can be reasonably inferred from the passage?

Top Courses for CLAT

6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer?
Question Description
6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? for CLAT 2025 is part of CLAT preparation. The Question and answers have been prepared according to the CLAT exam syllabus. Information about 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for CLAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer?.
Solutions for 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for CLAT. Download more important topics, notes, lectures and mock test series for CLAT Exam by signing up for free.
Here you can find the meaning of 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 6 men can complete a certain piece of work in 4 days, whereas 8 women can complete the same piece of work in 4 days. 3 men start working on the job and they quit the job after working for 2 days. How many women should be employed to complete the remaining work, if it is to be completed within the next 3 days?a)6 womenb)9 womenc)8 womend)24 womenCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice CLAT tests.
Explore Courses for CLAT exam

Top Courses for CLAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev