Question Description
A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer?.
Solutions for A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer?, a detailed solution for A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.