CAT Exam  >  CAT Questions  >   A, B and C are assigned a piece of work whic... Start Learning for Free
A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:
  • a)
    18
  • b)
    20
  • c)
    15
  • d)
    12
  • e)
    17
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
A, B and C are assigned a piece of work which they can complete by wo...
Given:
- A, B, and C can complete a piece of work together in 15 days.
- Their efficiencies are in the ratio 1:2:3.
- After completing 1/3 of the work, one person has to be withdrawn due to budget constraints.
- Their wages per day are in the ratio 3:5:6.

To find:
The number of days in which the remaining two persons can complete the work at optimal cost.

Solution:
Let the efficiencies of A, B, and C be x, 2x, and 3x respectively.

Efficiency is inversely proportional to the number of days taken to complete the work. Therefore, the number of days taken by A, B, and C to complete the work individually will be 15x, 7.5x, and 5x respectively.

Step 1: Calculating the cost per day for each person:
Let the wages per day of A, B, and C be 3y, 5y, and 6y respectively.

The cost per day for A = 3y / 15x = y / 5x
The cost per day for B = 5y / 7.5x = 2y / 3x
The cost per day for C = 6y / 5x = 6y / 5x

Step 2: Calculating the cost of completing 1/3rd of the work:
Let the total work be W. Then 1/3rd of the work = W/3.

The work done by A, B, and C individually in completing 1/3rd of the work is:
Work done by A = (W/3) * (1/15x) = W/45x
Work done by B = (W/3) * (1/7.5x) = W/22.5x
Work done by C = (W/3) * (1/5x) = W/15x

Step 3: Calculating the cost for completing 1/3rd of the work:
The cost for completing 1/3rd of the work is:
Cost for A = (W/45x) * (y/5x) = Wy / 225x^2
Cost for B = (W/22.5x) * (2y/3x) = 2Wy / 67.5x^2
Cost for C = (W/15x) * (6y/5x) = 6Wy / 75x^2

Step 4: Calculating the remaining work:
The remaining work after completing 1/3rd of the work is:
Remaining work = W - (W/3) = 2W/3

Step 5: Calculating the number of days required to complete the remaining work:
The remaining work can be completed by two people with optimal cost.

Let the efficiencies of the remaining two people be 2x and 3x respectively (after one person is withdrawn).

The number of days taken by the remaining two people to complete the remaining work is:
Number of days = (2W/3) / (2x +
Free Test
Community Answer
A, B and C are assigned a piece of work which they can complete by wo...
Let A take x days to complete the work, B x/2 and C x/3.
So, 1/x + 1/(x/2) + 1/(x/3) = 1/15
Solving, 6/x = 1/15 or x = 90.
So A will take 90 days, B 45 days, C 30 days to do the work.
Wages per unit of work for A,B,C are in the ratio: 3/1 : 5/2 : 6/3 = 3:2.5:2
So, A is the most expensive for unit of work, and will be withdrawn.
B & C in 1 day can do 1/45 + 1/30 = 1/18 th of work, or B and C working together will take 18 days to do the complete work
Time taken by B & C to do 2/3 rd of work = 2x18/3 = 12 days
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

Top Courses for CAT

A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer?
Question Description
A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer?.
Solutions for A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer?, a detailed solution for A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A, B and C are assigned a piece of work which they can complete by working together in 15 days. Their efficiencies (measured in terms of rate of doing work) are in the ratio 1 : 2 : 3. After 1/3 of the work is completed, one of them has to be withdrawn due to budget constraint. Their wages per day are in the ratio 3 : 5 : 6. The number of days in which the remaining two persons can complete the work (at optimal cost) is:a)18b)20c)15d)12e)17Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev