Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?
  • a)
    40
  • b)
    60
  • c)
    100
  • d)
    None of these
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5...
View all questions of this test
Most Upvoted Answer
Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5...
Given data:
- Alok, Mithilesh, and Bimlesh started a work
- After completing 1/5th of the work Bimlesh left
- Alok and Mithilesh then worked for 20 days
- Bimlesh completed the remaining portion of the work in 12 days
- Bimlesh takes 40 days to complete the work

To find:
In how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work are the same.

Approach:
Let the total work be denoted by 'W'.
Let the efficiency of Alok, Mithilesh, and Bimlesh be denoted by 'a', 'm', and 'b' respectively.
According to the given data:
- After completing 1/5th of the work, Bimlesh left, so the remaining work is 4/5th of W.
- Alok and Mithilesh worked for 20 days, so their total work done in 20 days is (20 * (a+m)).
- Bimlesh completed the remaining 4/5th of the work in 12 days, so his work done in 12 days is (4/5 * W).
- Bimlesh takes 40 days to complete the entire work, so his work done in 40 days is W.

Using the above data, we can form equations and solve for 'a' and 'm' to find the time taken by each of them to complete the work.

Calculation:
- After completing 1/5th of the work, Bimlesh left, so the remaining work is 4/5th of W.
- Alok and Mithilesh worked for 20 days, so their total work done in 20 days is (20 * (a+m)).
- Bimlesh completed the remaining 4/5th of the work in 12 days, so his work done in 12 days is (4/5 * W).
- Bimlesh takes 40 days to complete the entire work, so his work done in 40 days is W.

Using the above data, we can form equations and solve for 'a' and 'm' to find the time taken by each of them to complete the work.

Equations:
1. (1/5 * W) + (4/5 * W) = W (Total work done by Bimlesh)
2. (20 * (a+m)) + (4/5 * W) = W (Total work done by Alok, Mithilesh, and Bimlesh)
3. (40 * b) = W (Total work done by Bimlesh)

Solving these equations, we get:
a+m = (3/100) * W
b = (1/40) * W

Since the efficiencies of Alok, Mithilesh, and Bimlesh are the same, we can assume that 'a' = 'm' = 'x'.
So, from equation 1:
b = (4/5) * W
=> (1/40) * W = (4/5) * W
=> 1/40 = 4/5
This is not possible, hence the answer is 'None of these'.

Therefore, the correct answer is option 'D'.
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

Anjali, Bipasha, and Chitra visited an entertainment park that has four rides. Each ride lasts one hour and can accommodate one visitor at one point. All rides begin at 9 am and must be completed by 5 pm except for Ride-3, for which the last ride has to be completed by 1 pm. Ride gates open every 30 minutes, e.g. 10 am, 10:30 am, and so on. Whenever a ride gate opens, and there is no visitor inside, the first visitor waiting in the queue buys the ticket just before taking the ride. The ticket prices are Rs. 20, Rs. 50, Rs. 30 and Rs. 40 for Rides 1 to 4, respectively. Each of the three visitors took at least one ride and did not necessarily take all rides. None of them took the same ride more than once. The movement time from one ride to another is negligible, and a visitor leaves the ride immediately after the completion of the ride. No one takes a break inside the park unless mentioned explicitly.The following information is also known. Chitra never waited in the queue and completed her visit by 11 am after spending Rs. 50 to pay for the ticket(s). Anjali took Ride-1 at 11 am after waiting for 30 mins for Chitra to complete it. It was the only ride where Anjali waited. Bipasha began her first of three rides at 11:30 am. All three visitors incurred the same amount of ticket expense by 12:15 pm. The last ride taken by Anjali and Bipasha was the same, where Bipasha waited 30 mins for Anjali to complete her ride.Before standing in the queue for that ride, Bipasha took a 1-hour coffee break after completing her previous ride.How many rides did Anjali and Chitra take in total? Correct answer is '6'. Can you explain this answer?

Anjali, Bipasha, and Chitra visited an entertainment park that has four rides. Each ride lasts one hour and can accommodate one visitor at one point. All rides begin at 9 am and must be completed by 5 pm except for Ride-3, for which the last ride has to be completed by 1 pm. Ride gates open every 30 minutes, e.g. 10 am, 10:30 am, and so on. Whenever a ride gate opens, and there is no visitor inside, the first visitor waiting in the queue buys the ticket just before taking the ride. The ticket prices are Rs. 20, Rs. 50, Rs. 30 and Rs. 40 for Rides 1 to 4, respectively. Each of the three visitors took at least one ride and did not necessarily take all rides. None of them took the same ride more than once. The movement time from one ride to another is negligible, and a visitor leaves the ride immediately after the completion of the ride. No one takes a break inside the park unless mentioned explicitly.The following information is also known. Chitra never waited in the queue and completed her visit by 11 am after spending Rs. 50 to pay for the ticket(s). Anjali took Ride-1 at 11 am after waiting for 30 mins for Chitra to complete it. It was the only ride where Anjali waited. Bipasha began her first of three rides at 11:30 am. All three visitors incurred the same amount of ticket expense by 12:15 pm. The last ride taken by Anjali and Bipasha was the same, where Bipasha waited 30 mins for Anjali to complete her ride.Before standing in the queue for that ride, Bipasha took a 1-hour coffee break after completing her previous ride.What was the total amount spent on tickets (in Rs.) by Anjali? Correct answer is '140'. Can you explain this answer?

Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer?
Question Description
Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Alok, Mithilesh, and Bimlesh started a work and after completing 1 / 5th of the work Bimlesh left. Alok and Mithilesh then worked for 20 days. Bimlesh then took over from Alok and Mithilesh and completed the remaining portion of the work in 12 days. If Bimlesh takes 40 days to complete the work, in how many days would Alok alone or Mithilesh alone complete the work if the efficiencies with which they work is the same?a)40b)60c)100d)None of theseCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev