Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will be
  • a)
    0.864cm
  • b)
    8.64cm
  • c)
    86.4cm
  • d)
    864cm
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Given that the base period is 100 days and the duty of canal is 1000 h...
To calculate the depth of water in a canal, we need to use the following formula:

Depth of water = Duty of canal / Base period

Given that the duty of the canal is 1000 hectares per comec and the base period is 100 days, we can substitute these values into the formula to find the depth of water.

**Calculating the Depth of Water:**

Depth of water = 1000 hectares / 100 days

Now, we need to convert the area from hectares to square centimeters and the time from days to seconds to ensure consistent units.

1 hectare = 10,000 square meters
1 square meter = 10,000 square centimeters

1000 hectares = 1000 * 10,000 * 10,000 square centimeters

1 day = 24 * 60 * 60 seconds

100 days = 100 * 24 * 60 * 60 seconds

Now, we can substitute these converted values into the formula:

Depth of water = (1000 * 10,000 * 10,000 square centimeters) / (100 * 24 * 60 * 60 seconds)

Simplifying this equation, we get:

Depth of water = 100,000,000,000 square centimeters / 864,000 seconds

Simplifying further, we get:

Depth of water = 115,740.74 square centimeters

Therefore, the depth of water in the canal is 86.4 cm (rounded to one decimal place).

Hence, the correct answer is option 'C' (86.4 cm).
Free Test
Community Answer
Given that the base period is 100 days and the duty of canal is 1000 h...
7
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer?
Question Description
Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Given that the base period is 100 days and the duty of canal is 1000 hectares per comec, thedepth of water will bea)0.864cmb)8.64cmc)86.4cmd)864cmCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev