The controller required to handle fast process load changes is:
  • a)
    PD controller
  • b)
    PI Controller
  • c)
    PID Controller
  • d)
    None of the above
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
The controller required to handle fast process load changes is:a)PD co...
The Proportional Derivative controller is preferred to handle fast process load changes.
Hence, the correct answer is an option (a).
Free Test
Community Answer
The controller required to handle fast process load changes is:a)PD co...
Fast process load changes can be challenging to handle, as they can lead to significant disturbances in the system. In order to effectively control the process and maintain stability, a suitable controller is required. Among the given options, the PD controller is the most appropriate choice for handling fast process load changes.

Below are the reasons why a PD controller is the best option:

1. Proportional Control:
- The PD controller consists of a proportional term (P), which provides control action based on the current error between the desired setpoint and the measured process variable.
- The proportional control helps in reducing the steady-state error and provides an initial corrective action based on the magnitude of the error.

2. Derivative Control:
- The derivative term (D) in the PD controller provides control action based on the rate of change of the error.
- In the case of fast process load changes, the rate of change of the error can be high. The derivative control helps in capturing this rate of change and provides additional corrective action accordingly.
- By considering the rate of change, the derivative control helps in predicting the future behavior of the process variable and responds quickly to any sudden changes.

3. Handling Fast Load Changes:
- Fast process load changes can lead to large deviations in the process variable, which can result in instability and poor control performance.
- The PD controller with its proportional and derivative terms is effective in handling fast load changes.
- The proportional term provides immediate control action based on the current error, while the derivative term helps in capturing the rapid changes and reacting accordingly.
- The combination of proportional and derivative control enables the PD controller to quickly respond to fast load changes and stabilize the process variable.

In summary, the PD controller is the most suitable option for handling fast process load changes due to its ability to provide immediate control action based on the current error (proportional control) and respond to rapid changes in the error (derivative control).
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer?
Question Description
The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The controller required to handle fast process load changes is:a)PD controllerb)PI Controllerc)PID Controllerd)None of the aboveCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev