CAT Exam  >  CAT Questions  >   3 friends Amar, Bikram, and Charan can compl... Start Learning for Free
3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed is
  • a)
    9 days
  • b)
    11 days
  • c)
    10 days
  • d)
    12 days
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
3 friends Amar, Bikram, and Charan can complete a piece of work in 12...
Given:
- Amar can complete the work in 12 days.
- Bikram can complete the work in 15 days.
- Charan can complete the work in 9 days.
- The work is done in a cycle where Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats.

To find:
The number of days in which the work will be completed.

Explanation:
To solve this problem, we need to find the time taken for all three friends to complete the work together in one cycle. Then, we can find the number of cycles required to complete the work.

Step 1: Find the work done by each friend in one day:
- Amar can complete 1/12th of the work in one day.
- Bikram can complete 1/15th of the work in one day.
- Charan can complete 1/9th of the work in one day.

Step 2: Find the work done in each cycle:
In one cycle, the work done by each friend is as follows:
- Amar (day 1) = 1/12th of the work.
- Amar and Charan (day 2) = 1/12th + 1/9th = 7/36th of the work.
- Bikram (day 3) = 1/15th of the work.

Step 3: Find the total work done in one cycle:
The total work done in one cycle is the sum of the work done by each friend in that cycle:
1/12 + 7/36 + 1/15 = 5/18th of the work.

Step 4: Find the number of cycles required to complete the work:
To find the number of cycles required, we need to divide the total work (1 whole) by the work done in one cycle (5/18):
Number of cycles = 1 / (5/18) = 18/5 ≈ 3.6 (approx).

Since we cannot have a fraction of a cycle, we round up to the nearest whole number. Therefore, we need 4 cycles to complete the work.

Step 5: Find the number of days to complete the work:
In each cycle, 3 days are required for the work to be completed (Amar on day 1, Amar and Charan on day 2, and Bikram on day 3). Therefore, the total number of days required to complete the work is:
4 cycles x 3 days per cycle = 12 days.

So, the work will be completed in 12 days.

Therefore, the correct answer is option A) 12 days.
Free Test
Community Answer
3 friends Amar, Bikram, and Charan can complete a piece of work in 12...
Let the total amount of work to be done be 180 units.
⇒ Amar can do 180/12 = 15 units of work in a day.
Bikram can complete 180/15 = 12 units of work in a day
Charan can complete 180/9 = 20 units of work in a day.
On the first day, only Amar works. On the second day. both Amar and Charan work. On the third day, Bikram works.
Therefore, in a cycle of 3 days, 15+15+20+12=62 units of work will get completed.
In 2 cycles, 124 units of work will be completed.
180-124 = 56 units of work will be remaining after the second cycle (i.e 6 days).
Amar will complete 15 units of work on the seventh day. Amar and Charan will complete 15+20 = 35 units of work on the eighth day.
Therefore, by the end of 8 days, 124+15+15+20 = 174 units of work will be completed.
Bikram will complete the remaining 6 units of work on the ninth day.
Explore Courses for CAT exam

Similar CAT Doubts

3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer?
Question Description
3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer? for CAT 2025 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer?.
Solutions for 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 3 friends Amar, Bikram, and Charan can complete a piece of work in 12, 15, and 9 days respectively. If Amar works on day 1, Amar and Charan work on day 2, Bikram works on day 3, and the cycle repeats, then the number of days in which the work will be completed isa)9 daysb)11 daysc)10 daysd)12 daysCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev